Stakeholder Update

If you see unfamiliar placeholders or need to check which tools are connected, see CONNECTORS.md.

Generate a stakeholder update tailored to the audience and cadence.

Usage

/stakeholder-update $ARGUMENTS

Workflow

1. Determine Update Type

Ask the user what kind of update:

  • Weekly: Regular cadence update on progress, blockers, and next steps
  • Monthly: Higher-level summary with trends, milestones, and strategic alignment
  • Launch: Announcement of a feature or product launch with details and impact
  • Ad-hoc: One-off update for a specific situation (escalation, pivot, major decision)
2. Determine Audience

Ask who the update is for:

  • Executives / leadership: High-level, outcome-focused, strategic framing, brief
  • Engineering team: Technical detail, implementation context, blockers, decisions needed
  • Cross-functional partners: Context-appropriate detail, focus on shared goals and dependencies
  • Customers / external: Benefits-focused, clear timelines, no internal jargon
  • Board: Metrics-driven, strategic, risk-focused, very concise
3. Pull Context from Connected Tools

If ~~project tracker is connected:

  • Pull status of roadmap items and milestones
  • Identify completed items since last update
  • Surface items that are at risk or blocked
  • Pull sprint or iteration progress

If ~~chat is connected:

  • Search for relevant team discussions and decisions
  • Find blockers or issues raised in channels
  • Identify key decisions made asynchronously

If ~~meeting transcription is connected:

  • Pull recent meeting notes and discussion summaries
  • Find decisions and action items from relevant meetings

If ~~knowledge base is connected:

  • Search for recent meeting notes
  • Find decision documents or design reviews

If no tools are connected, ask the user to provide:

  • What was accomplished since the last update
  • Current blockers or risks
  • Key decisions made or needed
  • What is coming next
4. Generate the Update

Structure the update for the target audience using the templates and frameworks below.

For executives: TL;DR, status color (G/Y/R), key progress tied to goals, decisions made, risks with mitigation, specific asks, and next milestones. Keep it under 300 words.

For engineering: What shipped (with links), what is in progress (with owners), blockers, decisions needed (with options and recommendation), and what is coming next.

For cross-functional partners: What is coming that affects them, what you need from them (with deadlines), decisions that impact their team, and areas open for input.

For customers: What is new (framed as benefits), what is coming soon, known issues with workarounds, and how to provide feedback. No internal jargon.

For launch announcements: What launched, why it matters, key details (scope, availability, limitations), success metrics, rollout plan, and feedback channels.

5. Review and Deliver

After generating the update:

  • Ask if the user wants to adjust tone, detail level, or emphasis
  • Offer to format for the delivery channel (email, chat post, doc, slides)
  • If ~~chat is connected, offer to draft the message for sending

Update Templates by Audience

Executive / Leadership Update

Executives want: strategic context, progress against goals, risks that need their help, decisions that need their input.

Format:

Status: [Green / Yellow / Red]
TL;DR: [One sentence — the most important thing to know]
Progress:
- [Outcome achieved, tied to goal/OKR]
- [Milestone reached, with impact]
- [Key metric movement]
Risks:
- [Risk]: [Mitigation plan]. [Ask if needed].
Decisions needed:
- [Decision]: [Options with recommendation]. Need by [date].
Next milestones:
- [Milestone] — [Date]

Tips for executive updates:

  • Lead with the conclusion, not the journey. Executives want "we shipped X and it moved Y metric" not "we had 14 standups and resolved 23 tickets."
  • Keep it under 200 words. If they want more, they will ask.
  • Status color should reflect YOUR genuine assessment, not what you think they want to hear. Yellow is not a failure — it is good risk management.
  • Only include risks you want help with. Do not list risks you are already handling unless they need to know.
  • Asks must be specific: "Decision on X by Friday" not "support needed."
Engineering Team Update

Engineers want: clear priorities, technical context, blockers resolved, decisions that affect their work.

Format:

Shipped:
- [Feature/fix] — [Link to PR/ticket]. [Impact if notable].
In progress:
- [Item] — [Owner]. [Expected completion]. [Blockers if any].
Decisions:
- [Decision made]: [Rationale]. [Link to ADR if exists].
- [Decision needed]: [Context]. [Options]. [Recommendation].
Priority changes:
- [What changed and why]
Coming up:
- [Next items] — [Context on why these are next]

Tips for engineering updates:

  • Link to specific tickets, PRs, and documents. Engineers want to click through for details.
  • When priorities change, explain why. Engineers are more bought in when they understand the reason.
  • Be explicit about what is blocking them and what you are doing to unblock it.
  • Do not waste their time with information that does not affect their work.
Cross-Functional Partner Update

Partners (design, marketing, sales, support) want: what is coming that affects them, what they need to prepare for, how to give input.

Format:

What's coming:
- [Feature/launch] — [Date]. [What this means for your team].
What we need from you:
- [Specific ask] — [Context]. By [date].
Decisions made:
- [Decision] — [How it affects your team].
Open for input:
- [Topic we'd love feedback on] — [How to provide it].
Customer / External Update

Customers want: what is new, what is coming, how it benefits them, how to get started.

Format:

What's new:
- [Feature] — [Benefit in customer terms]. [How to use it / link].
Coming soon:
- [Feature] — [Expected timing]. [Why it matters to you].
Known issues:
- [Issue] — [Status]. [Workaround if available].
Feedback:
- [How to share feedback or request features]

Tips for customer updates:

  • No internal jargon. No ticket numbers. No technical implementation details.
  • Frame everything in terms of what the customer can now DO, not what you built.
  • Be honest about timelines but do not overcommit. "Later this quarter" is better than a date you might miss.
  • Only mention known issues if they are customer-impacting and you have a resolution plan.

Status Reporting Framework

Green / Yellow / Red Status

Green (On Track):

  • Progressing as planned
  • No significant risks or blockers
  • On track to meet commitments and deadlines
  • Use Green when things are genuinely going well — not as a default

Yellow (At Risk):

  • Progress is slower than planned, or a risk has materialized
  • Mitigation is underway but outcome is uncertain
  • May miss commitments without intervention or scope adjustment
  • Use Yellow proactively — the earlier you flag risk, the more options you have

Red (Off Track):

  • Significantly behind plan
  • Major blocker or risk without clear mitigation
  • Will miss commitments without significant intervention (scope cut, resource addition, timeline extension)
  • Use Red when you genuinely need help. Do not wait until it is too late.
When to Change Status
  • Move to Yellow at the FIRST sign of risk, not when you are sure things are bad
  • Move to Red when you have exhausted your own options and need escalation
  • Move back to Green only when the risk is genuinely resolved, not just paused
  • Document what changed when you change status — "Moved to Yellow because [reason]"

Risk Communication

ROAM Framework for Risk Management
  • Resolved: Risk is no longer a concern. Document how it was resolved.
  • Owned: Risk is acknowledged and someone is actively managing it. State the owner and the mitigation plan.
  • Accepted: Risk is known but we are choosing to proceed without mitigation. Document the rationale.
  • Mitigated: Actions have reduced the risk to an acceptable level. Document what was done.
Communicating Risks Effectively
  1. State the risk clearly: "There is a risk that [thing] happens because [reason]"
  2. Quantify the impact: "If this happens, the consequence is [impact]"
  3. State the likelihood: "This is [likely/possible/unlikely] because [evidence]"
  4. Present the mitigation: "We are managing this by [actions]"
  5. Make the ask: "We need [specific help] to further reduce this risk"
Common Mistakes in Risk Communication
  • Burying risks in good news. Lead with risks when they are important.
  • Being vague: "There might be some delays" — specify what, how long, and why.
  • Presenting risks without mitigations. Every risk should come with a plan.
  • Waiting too long. A risk communicated early is a planning input. A risk communicated late is a fire drill.

Decision Documentation (ADRs)

Architecture Decision Record Format

Document important decisions for future reference:

# [Decision Title]
## Status
[Proposed / Accepted / Deprecated / Superseded by ADR-XXX]
## Context
What is the situation that requires a decision? What forces are at play?
## Decision
What did we decide? State the decision clearly and directly.
## Consequences
What are the implications of this decision?
- Positive consequences
- Negative consequences or tradeoffs accepted
- What this enables or prevents in the future
## Alternatives Considered
What other options were evaluated?
For each: what was it, why was it rejected?
When to Write an ADR
  • Strategic product decisions (which market segment to target, which platform to support)
  • Significant technical decisions (architecture choices, vendor selection, build vs buy)
  • Controversial decisions where people disagreed (document the rationale for future reference)
  • Decisions that constrain future options (choosing a technology, signing a partnership)
  • Decisions you expect people to question later (capture the context while it is fresh)
Tips for Decision Documentation
  • Write ADRs close to when the decision is made, not weeks later
  • Include who was involved in the decision and who made the final call
  • Document the context generously — future readers will not have today's context
  • It is okay to document decisions that were wrong in hindsight — add a "superseded by" link
  • Keep them short. One page is better than five.

Meeting Facilitation

Stand-up / Daily Sync

Purpose: Surface blockers, coordinate work, maintain momentum. Format: Each person shares:

  • What they accomplished since last sync
  • What they are working on next
  • What is blocking them

Facilitation tips:

  • Keep it to 15 minutes. If discussions emerge, take them offline.
  • Focus on blockers — this is the highest-value part of standup
  • Track blockers and follow up on resolution
  • Cancel standup if there is nothing to sync on. Respect people's time.
Sprint / Iteration Planning

Purpose: Commit to work for the next sprint. Align on priorities and scope. Format:

  1. Review: what shipped last sprint, what carried over, what was cut
  2. Priorities: what are the most important things to accomplish this sprint
  3. Capacity: how much can the team take on (account for PTO, on-call, meetings)
  4. Commitment: select items from the backlog that fit capacity and priorities
  5. Dependencies: flag any cross-team or external dependencies

Facilitation tips:

  • Come with a proposed priority order. Do not ask the team to prioritize from scratch.
  • Push back on overcommitment. It is better to commit to less and deliver reliably.
  • Ensure every item has a clear owner and clear acceptance criteria.
  • Flag items that are underscoped or have hidden complexity.

This is the start of the file. Read the full SKILL.md on GitHub.

Security

  • Security scanPassed, 100 of 100Pattern checks on the skill's files. Certified 13 Mar 2026.
  • Model reviewPassed

Quality evaluation

  • Task evaluationNot runNo evaluation yet. Run one in Skill Studio.

Source

Popularity

Repository stars
9,044
Repository forks
994
7-day trend score
46

Stars and forks are for the whole GitHub repository, not this skill alone. Refreshed 24 Mar 2026, 8 months ago.

Works with

Any agent vskill installs to: 56 targets in all. These 39 have a page on this site.

  • Claude Code
  • Cursor
  • GitHub Copilot
  • Windsurf
  • Codex
  • Gemini CLI
  • Cline
  • Amp
  • Roo Code
  • Goose
  • Continue
  • Kilo Code
  • Junie
  • Trae
  • OpenHands
  • Qwen Code
  • AI Agent
  • Tabnine Chat
  • Sourcegraph Cody
  • Amazon Q
  • Firebase Genkit
  • Sweep
  • Devin
  • Phind
  • Mentat
  • Claude Desktop
  • Aider
  • GPT Pilot
  • Plandex
  • bolt.new
  • v0
  • Replit Agent
  • Anse
  • TypingMind
  • BetterChatGPT
  • LibreChat
  • Warp AI
  • Pieces