SKILL.md · 77 lines · 3.3 KB

version: "1.0.0" name: rtl-p3-uarch-design description: "Phase 3 uArch design: maps P2 blocks to sub-blocks with clock domains, FSM/SRAM allocation, BFM validation. Use for 'uarch', 'microarchitecture', 'Phase 3'." user-invocable: true argument-hint: "[--resume | uarch-focus]" allowed-tools: Bash, Read, Write, Edit, Task, Grep, Glob, AskUserQuestion


<Purpose> Execute Phase 3 μArch design pipeline. Concretizes architecture blocks into implementable microarchitecture specifications with clock domains, protocol assignments, register/SRAM/FSM allocation, and BFM validation. </Purpose>

<Use_When>

  • Phase 2 architecture is complete and μArch design is needed
  • User says "microarchitecture", "uarch", "Phase 3"
  • Need detailed module specs before RTL implementation

</Use_When>

<Do_Not_Use_When>

  • Phase 2 architecture is not complete (run p2-arch-design first)
  • Already have μArch specs and need RTL (use rtl-p4-implement)
  • Need architecture-level design (use p2-arch-design)

</Do_Not_Use_When>

Prerequisites

Phase 2 completion required:

  • docs/phase-2-architecture/architecture.md must exist
  • refc/ directory with C reference model must exist

If prerequisites are missing: WARNING — recommend running /rtl-agent-team:p2-arch-design. Proceed with available artifacts — orchestrator will adapt scope.

Execution

Task(subagent_type="rtl-agent-team:p3-uarch-orchestrator", prompt="Execute Phase 3 uArch design. User input: $ARGUMENTS")

Do not perform any work directly. The orchestrator agent manages domain consultation, parallel uarch design + BFM development, BFM validation gate, and 5-reviewer dynamic-convergence review (min 2, max 5 rounds).

Workflow Notes

  • Open Resolution: resolve all OPEN-2-* items from Phase 2 open-requirements.json
  • Zero-Opens Invariant: no unresolved OPEN-* items may pass to Phase 4
  • Compliance Check: verify REQ-U-* uarch requirements against P1+P2 iron requirements
  • Exit gate includes compliance-pass and zero-remaining-opens

P3 Exit Gate: Acceptance Criteria Advisory

Every REQ-U-* in docs/phase-3-uarch/iron-requirements.json should have ≥1 acceptance_criteria entry. This is an advisory check (WARNING, not hard-block):

  • If any REQ-U-* has no acceptance_criteria (absent or empty array []): emit WARNING listing

the affected REQ IDs

  • Prompt uarch-designer to add missing criteria before P3 exit
  • Proceed even if some REQ-U-* lack AC — downstream verification will operate at req_ids level

(backward compatible)

P3 Exit Gate: Decomposition Completeness Advisory

After iron-requirements.json is finalized, verify decomposition completeness:

  1. Read docs/phase-1-research/iron-requirements.json — collect all Critical/High REQ-F-*
  2. Read docs/phase-2-architecture/iron-requirements.json — collect all Critical/High REQ-A-*
  3. For each Critical/High REQ-F-: check if at least one REQ-U- has it in traces_to
  4. For each Critical/High REQ-A-: check if at least one REQ-U- has it in traces_to
  5. Report:
  • COVERED: upstream REQ has ≥1 REQ-U-* tracing to it
  • UNCOVERED: no REQ-U-* traces to this upstream REQ → WARNING

This is advisory (WARNING, not hard-block). UNCOVERED Critical requirements should be investigated — they may indicate a decomposition gap or an intentional architecture decision (document rationale if intentional).