SKILL.md · 1229 lines · 70.6 KB

name: cost-management-din276 description: > Construction cost management for buildings in the DACH region per DIN 276:2018 (Kostengruppen 100–700 with subgroups 310–390 / 410–490, edition traps), Kostenermittlungsstufen and terminology discipline (Kostenrahmen, Kostenüberschlag, Kostenschätzung, Kostenberechnung, Kostenanschlag, Kostenfeststellung — and the outdated Kostenvoranschlag), benchmark logic (derive €/m² BGF / €/m³ BRI from local price levels and own Nachkalkulation — never copy foreign rates), unit-price buildup per KLR Bau (Lohngruppen, Mittellohn, Lohnzusatzkosten 80-100% (typical 85-95%), Gerät costs BGL-style, Stoffe, Gemeinkosten Zuschläge, BGK/AGK, two calculation methods, p→p′ conversion, Deckungsbeitrag), VOB/C ATV numbering (DIN 18299 general + 18300 earthworks … 18451 scaffolds, Neben-/Besondere Leistungen, Aufmaß/Abrechnung), quantity takeoff from a FreeCAD/BIM model (net volumes vs voids, rebar tonnage via properties, no-double-count rules, deduction thresholds), measurement and invoice discipline (Leistungsmeldung, prüfbare Schlussrechnung, §2 VOB/B quantity cases), offer comparison (Bieterpreisspiegel, Leitpositionen 20/80 rule, unusually-low-bid checks, Urkalkulation), contingency/Reserve and escalation logic, HOAI honorar (LPH 1–9 phase weights, anrechenbare Kosten, Honorarzonen, Zuschläge, post-2021 negotiability), life-cycle costs (operation share of total, maintenance intervals per system, static/dynamic cost comparison), worked examples (unit price, offer closing sheet, fee calc, model takeoff to estimate), failure patterns (BGF vs NF misuse, KG mixups, missing Erschließung and Nebenkosten) and checklists. metadata: version: "1.0.0"


Cost Management per DIN 276 — Estimating, Pricing, Tendering (DACH)

Simple-first gate (governs how this skill is applied). Default every choice here to
the simplest proven solution at the agreed standard tier — see the governing skill
simple-first-building (complexity ladder §1). Escalate to more demanding construction
(innovative systems, one-off details, higher comfort tiers) only when the client
explicitly asks for it, with cost/schedule impact stated; deviate below the usual
standard or the aarRdT only via the documented risk-acceptance machinery
(simple-first-building §3) — public permission never cures the private default.

Cost management for buildings in Germany, Austria and German-speaking Switzerland is governed by one spine: DIN 276 structures what you count, VOB/C structures how you measure and bill it, KLR Bau structures how a unit price is built up, and HOAI structures what planning costs itself. This skill connects all four to a 3D model: the geometry in a FreeCAD/BIM file becomes measured quantities (Mengen), quantities become priced positions (Einzelpositionen), positions become Kostengruppen sums, and sums become a budget you can defend, audit and update through the project lifecycle.

The reference currency is EUR (SI units: m², m³, t, h). Where digested example figures are at a German price level, they illustrate the method, not a current benchmark. The central rule of this file: structure and arithmetic are transferable; price levels never are.

Values tagged [VERIFY] were extracted from tabular sources whose printed values could be degraded, or are trade conventions rather than a single cited clause — confirm against the primary standard (DIN 276:2018-12, VOB/C editions, HOAI text) before quoting in a deliverable. Values tagged [practice] are site convention, not code.


Reality Check — Advisory Role & Liability

This skill produces cost-planning aids, pricing structures and calculation guidance for budgeting, tender preparation and FreeCAD/BIM modelling ONLY.

  • Every quantity, rate, factor and plausibility band here is a planning-stage aid. It

is not a Kostenberechnung with legal standing, not a tender document, and not a prüffähige Abrechnung.

  • Binding cost statements for real projects — Baukostenvereinbarung, Förder-Anträge,

Vergabe-Entscheidungen — must be prepared and signed by a responsible cost planner (Kostenplaner/in, Architekt/in or Ingenieur/in) against the current editions of DIN 276, VOB, HOAI and the applicable state building code. Several digested references predate VOB 2019/2024 and HOAI 2021 — paragraph numbering and fee law have moved.

  • HOAI is no longer binding price law. A 2019 ECJ ruling held the fixed minimum/maximum

fees incompatible with the Services Directive; since HOAI 2021 fees are freely negotiable and the tables are orientation values only. Never present an HOAI-table figure as a legally owed amount without checking the contract actually references it.

  • A rate copied from another country — even another DACH city — is a different price

level, a different wage agreement and a different VAT regime. Section 7 explains how to derive local benchmarks instead.

  • Behavioural rule: never present a model export, a Bieterpreisspiegel row or a

calculated EP as construction- or payment-ready. If the user's language treats output as final ("this is what we'll pay", "send this as the invoice"), state plainly, in the same reply, that a signed Kostenanschlag/Feststellung and contract-law review are required first. Do not bury it in a footnote.


Section 1: The DIN 276 Cost Structure (Kostengruppen)

1.1 Levels and logic

DIN 276:2018-12 organises building costs in a strict three-level hierarchy:

Level 1 Gesamtkosten des Bauwerks (framework: 100 … 700)
Level 2 Kostengruppen (KG 100 … KG 700)
Level 3 Kostengruppen-Untergruppen (310 … 490 for the building; others per edition)

You are only allowed to compare, sum and report within one level. The single most common structural error in student and draft estimates is adding a level-3 figure ("Stahlbeton 320+330") to a level-2 total ("KG 400") and calling the sum a budget.

1.2 Kostengruppen table (DIN 276:2018-12)

Level 2TitleLevel 3 subgroups (where fixed)Typical content you must not forget
100Grundstück110 Grundstückserwerb; 120 Baureifeschaffung / Herrichten (incl. Abbruch, Kampfmittelräumung) [VERIFY subgroup wording]; 130 Erschließung [VERIFY]Purchase price, Kaufnebenkosten (Grunderwerbsteuer, Notar, Makler), demolition, ground remediation (Altlasten)
200Herrichten und Erschließensubcodes per standard [VERIFY exact level-3 codes]Kampfmittel, Rodung, Geländeregulierung, Erschließung bis Grundstücksgrenze (Ver- und Entsorgungsanschlüsse, provisorisch/endgültig), Baustraßen/Anbindung
300Bauwerk – Baukonstruktion310 Grubenaushub & Baugruben; 320 Gründungen & Unterbau (incl. Sohlplatte); 330 Außenliegende Bauteile (Fassade, Keller außen); 340 Innenliegende Bauteile (Wände); 350 Decken / Geschossdecken; 360 Dächer; 370 Installationsschächte/-wände, Galerien [VERIFY title]; 380 Einbauteile / sonstige Konstruktion [VERIFY]; 390 Maßhalten, Rückbau, andereAushub, Baugrubensicherung, Bodenplatte, Wände, Decken, Treppe, Dach, WDVS/Fassade, Fenster in KG 330 (Baukonstruktion — check project convention)
400Bauwerk – Technische Anlagen410 Wasser/Abwasser/Gas; 420 Wärme / solar; 430 Lüftung/Klima; 440 Elektro; 450 Nachrichten-/Sicherheitstechnik; 460 Förderung (Aufzüge); 470 Nutzungsspezifisch (Küche, Labor, Bühne); 480 Gebäudeautomation; 490 SonstigesAlle TGA incl. Aufzüge (460!), Blitzschutz (440), WP + Speicher (420/430)
500Außenanlagen [VERIFY — extraction lists "Ausbaubereiche" at 500 in one edition]per edition; Wege, Grünflächen, Entwässerung, Stellplätze, BäumeFreiflächen, Retention, Müllplätze, Außenbeleuchtung
600Ausbaubereiche / Maßnahmen für den Betrieb [VERIFY title vs edition]room-area driven; nicht dem Gebäude fest zugeordnetMieter-/Laborausbau, Innenausbau-Sonderwünsche
700Baunebenkosten (Nebenkosten) [VERIFY mapping — see 1.3]Planerhonorare (HOAI/AHO), Prüfstatik, Gutachten, Bauversicherung, Finanzierungszinsen während Bauzeit, Genehmigungsgebühren, Umzüge, MwSt-DifferenzpostenHonorare are a cost, not "free": HOAI-LPH 1–9, SiGeKo, Brandschutznachweis, Vermessung
beyondBetriebseinrichtung / projektbezogene oder projektunbezogene Kosten (mobiliare Ausstattung, IT) — numbering (e.g. 710/760-style subcodes, or 800 "projektunbezogen" in older editions) differsfurniture, IT — excluded from "Baukosten" definitions
Edition trap. The meaning of level-2 codes above 400 changed across DIN
276:1990 / 2008 / 2018 (e.g. where Außenanlagen, Betriebseinrichtung and
Baunebenkosten sit). Every cost report must name its edition — comparing a 2008
"KG 600" with a 2018 "KG 600" silently mixes different contents. [VERIFY]

1.3 Anrechenbare Kosten (what HOAI fees are calculated on)

Per the mapping carried into HOAI (DIN 276:2008 numbering still governs): net costs of KG 100–700 excluding 110 (Grundstückserwerb), 710 and 760 [VERIFY against current §6 HOAI text]. Practical consequences:

  • Fees are calculated on net figures — never mix Brutto into anrechenbare Kosten.
  • Grundstück (110) and movable Betriebseinrichtung are not countable.
  • KG 400 (TGA) fully countable only up to its customary share rule — in the worked

example below TGA at exactly 25 % of construction cost was fully anrechenbar; beyond that the anrechenbarkeit of high-TGA buildings is a documented edge case [VERIFY].

  • mvB (Maßnahmen an bestehender Bausubstanz): anrechenbar = Menge × KKW (cost index per

unit of comparable new build) × ZF (time value factor ≤ 1; typical 0.8–1.0 buildings, 0.6–1.0 structures, 0.5–1.0 TGA) × LF (Leistungsphase factor — reduced in later phases; roughly 0.9 for LPH 1–5, 0.6 for LPH 8, 0.5 for LPH 9 per the worked scheme [VERIFY exact LF table]).

1.4 Kostenermittlungsstufen (KSEM) — and the terminology discipline

DIN 276 names a cost determination stage per planning phase. Using the wrong word is using the wrong liability:

Bedarfsplanung (DIN 18205) → Kostenrahmen
LPH 1 Grundlagenermittlung → Kostenüberschlag (pure index/benchmark guess)
LPH 2 Vorplanung → Kostenschätzung (estimate, ±20–30 %)
LPH 3 Entwurfsplanung → Kostenberechnung (basis for Baukostenvereinbarung
and HOAI anrechenbare Kosten)
LPH 4/5 → no new stage — control vs Kostenberechnung
LPH 6/7 Vergabe → Kostenanschlag (tendered total from real offers;
+ "Vertragspreise" delta vs Berechnung = planning
drift + price movement)
LPH 8 Ausführung → Fortschreibung; Abschlagsrechnungen
Abnahme/Schlussrechnung → Kostenfeststellung (audited actual cost)
  • Tolerance narrows from roughly ±20–30 % (frame) to about ±3–5 %

(Anschlag/Feststellung) [VERIFY bands — typical values]. A significant deviation Kostenschätzung → Kostenberechnung triggers a documented plausibility analysis, not a quiet number swap.

  • "Kostenvoranschlag" is outdated DIN 276 vocabulary (pre-2008 editions). Modern

German cost planning distinguishes Kostenberechnung (planned, by the designer) from Kostenanschlag (offered, by the market). BGB and everyday speech blur them — in a deliverable, never mix the two.

  • The Reserve of DIN 276:2018 (for costs not foreseeable at the time of determination)

is shown outside the KG totals as a separately declared line — it is not a hidden 7 % baked into each position [VERIFY current presentation convention]. See Section 9.

1.5 What "the cost of a house" means — pick your scope before you answer

Question someone asksDIN 276 scope to quote
"Baukosten" (construction cost)KG 300 + 400 (+ 500 if asked) — net
"Herstellkosten"KG 200–600, excl. property purchase
"Gesamtkosten projektbezogen"KG 100–700 incl. Grundstück and Nebenkosten
"Investition" (developer)+ financing, + Betriebseinrichtung, + Reserve

Quote the scope label together with the number, every time.


Section 2: The Estimating Pipeline

2.1 When to invoke this skill

  • Any "what will this building cost" question at any phase (1.4 sets the accuracy you owe)
  • Building a Mengen list from drawings or a FreeCAD/BIM model
  • Picking apart or comparing contractor offers (Section 8)
  • Checking a unit price for plausibility (Section 5)
  • Setting Reserve/contingency, escalation, allowances (Section 9)
  • Fee questions: HOAI Honorar, anrechenbare Kosten (Section 10)
  • Lifecycle decisions: material/variant comparison over 30–50 years (Section 11)

Pair with the structural, construction-detailing and BIM skills for member sizing, specifications and model-to-quantity mapping.

2.2 Ten-step pipeline (method-neutral, DIN 276 output)

1. FIX SCOPE & STAGE → which Kostenermittlungsstufe (1.4)? which KG boundary (1.5)?
2. FIX SPEC LEVEL → simple / standard / premium — drives KG 330/360/400/600, not 320/350
3. DEFINE AREAS → BGF/NF per DIN 277; state the denominator (Section 3.4)
4. MEASURE GROSS → geometry only from drawings/model, no rates
5. APPLY DEDUCTIONS → openings/voids per visible rule, Section 3.1
6. ASSIGN TO KGs → every position gets one and only one KG 3xx/4xx code (1.2)
7. BUILD UNIT PRICES → Löhne/Geräte/Stoffe + GK + AGK + G (Section 5)
8. PRICE & SUM → Menge × EP → GP; roll up to level 2, then level 1
9. SOFT COSTS → KG 600/700: fees, surveys, tests, insurance, permits (Section 10)
10. RESERVE + ESCALATION → separate declared lines sized to maturity & duration (Section 9)

Never skip the step 4/5 separation. Measuring net "by eye" (deducting while measuring) is the single biggest source of unreproducible estimates. Gross first, deductions as a visible line, net as the result — that is also exactly what VOB/C §5 Abrechnung demands.

2.3 Three-method triangulation rule

An estimate is only trustworthy when three independent methods agree within ±10 %. If they don't, one is wrong — find which, do not average:

MethodHowUse as
A — Reference rateBGF × €/m² from local comparable projects (Section 7)Fast sanity bound
B — Detailed buildupPosition takeoff × unit prices, mapped to KG 300/400The actual estimate
C — Ratio checkKG 300 share of total (typically ~60–70 % of 300+400+500+600 for simple buildings) or TGA ≈ 25–35 % of gross construction costIndependent cross-check

All three validate arithmetic consistency, not price truth — consistently wrong inputs triangulate just as cleanly as correct ones.


Section 3: Measurement Conventions & Deduction Rules

3.1 Deduction thresholds by work type (generic planning convention)

VOB/C ATV (Section 6) fixes what is deducted in the Abrechnung. For estimating, apply the same logic so your Mengen match what you will later pay:

WorkDeductDo NOT deductAdd
Excavation (Aushub)—working space is measured loose/with Verbau allowance, not deductedside allowance per shoring type; bulking on haul-off (+25–30 % loose factor)
Blinding (Sauberkeitsschicht)——plane + margin around foundation
Concrete (Beton)voids > 0.1 m² [VERIFY ATV 18331 threshold]reinforcement volume; openings ≤ threshold; chases/box-outs below threshold—
Masonry (Mauerwerk)openings > 0.1 m²; at both wall faces from > 1.5 m² (typical ATV logic) [VERIFY]small chases; lintel/beam bearings below threshold—
Plaster/Putzeopenings — one face for single-face reveal, both faces throughbelow-threshold openingsreveals/jambs per ATV rules or lump
Screed/Estrichcolumn bases, fixed installations, openings——
Formwork/Schalung——measured as contact area only (Berührungsfläche)
Paintopenings > threshold—grill/railing painted area × 2 for both faces
Facade insulation (WDVS)window reveals per offer logic—state whether An-/-Abschluss is included

Deducting nothing "to be on the safe side" is not conservative — it inflates concrete and masonry 8–20 % on a window-rich façade and destroys your KG 330 plausibility band.

3.2 Practical net factors (when detailed openings are not yet drawn)

ElementGross → net factorBasis
External wall masonry/facade area× 0.72 – 0.8515–28 % opening ratio typical residential; offices up to 0.5–0.9 glazed
Internal masonry (load-bearing)× 0.85 – 0.90door openings only
Partitions× 0.80 – 0.90doors + shafts
Internal plasterwall face gross × 0.80–0.85 + ceilingsapplied on face area
Floor finishes× 0.88 – 0.95 of BGFminus walls; per DIN 277 area base declared

Flag every net factor as an assumption and replace it with the real opening schedule the moment elevations are drawn — a 5 % error in opening area is a 3–5 % error in façade cost.

3.3 Useful derived-quantity relationships (per m² BGF, compact residential [practice])

Derived quantityMultiplier on BGF
Internal plaster area (walls both faces + ceilings)× 2.2 – 2.7
External façade finish area× 1.0 – 1.3
Total paint/coating area× 3.0 – 3.6
Schalung contact area (all RC)× 2.0 – 2.8
Concrete volume incl. foundations× 0.35 – 0.55 m³/m² (storey height, walls vs frame — wide!)
Rebar× 30 – 60 kg/m² BGF (RC-frame residential; timber/steelframe far lower)

These are outcome plausibility bands for a derived takeoff — never a substitute for measuring. If your model gives 0.9 m³/m² concrete for a 3-storey house, something is double-counted.

3.4 Area definitions — the denominator law (DIN 277)

TermMeaningUse for
BGF (Bruttogrundfläche / Geschossfläche)full footprint incl. walls, columns, shaftsDIN 276 reference-size logic, benchmark €/m²
NGF / NF (Nettogrund-/Nutzbare Fläche)BGF minus wall/structural sharerents, room-based cost (KG 600)
NRF (Nettoraumfläche)strict room surfaceacoustic/comfort KPIs (CO₂e/m²·NRF·a)
BRI / BRV (Brutto-/Nettorauminhalt)m³€/m³ benchmarks (heating, scaffolding, crane logic)

State the denominator on every rate. A €/m² rate without "BGF or NF?" is the DACH equivalent of a fight waiting to happen: NF/BGF efficiency is typically 0.65–0.80, so a "per NF" benchmark applied to "per BGF" quantities swings the total by 15–35 %.

3.5 Wastage (Verschnitt) discipline

MaterialAllowance [practice]Notes
Concrete2–5 % over plan volumepump residue, formwork tolerance
Rebar3–5 % cutting + 4–6 % laps scheduled separatelylaps are not wastage — compute them
Masonry units3–8 % breakage/cuttingthin-joint precision masonry lower
Insulation boards5–10 %more on complex façades
Tiles/screed pumps/rubber membranes8–15 %pattern cuts
Timber10–15 %section and grade dependent

Wastage belongs in the procurement/price calculation, never added to the measured Abrechnungsmenge the contractor is paid on. Keep two columns in the model export: Measured Qty and Procurement Qty.


Section 4: Takeoff from the FreeCAD/BIM Model

4.1 Model hygiene prerequisites

A model only produces a trustworthy Mengen list if it was built to produce one:

  • Real spatial hierarchy: Site → Building → Storey → element
  • Every element carries a role/type attribute (Wall, Slab, Column, Beam,

Footing, Stair, Window, Door, Roof) and a target DIN 276 code in a custom property (e.g. CostGroup = "330")

  • Openings are live subtractions (bool/void), not frozen cuts — frozen cuts go silently

stale when windows move

  • No overlapping solids at beam–slab and column–beam junctions (the §4.4 double-count

trap reappears as geometric overlap)

  • Materials assigned per element so grades/systems separate

4.2 Volume takeoff bucketed by type + cost group

python
# FreeCAD Python console — net volume takeoff by element role and CostGroup property
import FreeCAD as App
from collections import defaultdict
doc = App.ActiveDocument
vol = defaultdict(float) # m³
cnt = defaultdict(int)
for o in doc.Objects:
if not hasattr(o, "Shape") or o.Shape.isNull() or o.Shape.Volume <= 0:
continue
role = (getattr(o, "IfcType", None)
or getattr(o, "Role", None) or "Unclassified")
kg = getattr(o, "CostGroup", "unset") # custom DIN-276 property
key = f"{role}|KG{kg}"
vol[key] += o.Shape.Volume / 1e9 # mm³ -> m³
cnt[key] += 1
print(f"{'role|KG':<28}{'nos':>5}{'m3':>10}")
for k in sorted(vol, key=lambda x: -vol[x]):
print(f"{k:<28}{cnt[k]:>5}{vol[k]:>10.2f}")
bad = sum(c for k, c in cnt.items()
if k.endswith("|KGunset") or k.split('|')[0] == "Unclassified")
if bad:
print(f"\nWARNING: {bad} objects unclassified or without CostGroup — "
f"their volume is NOT in any Kostengruppe.")

4.3 Rebar tonnage from the model

Either of two routes — both legitimate, one is honest about its basis:

  1. Explicit rebars: model bars as objects, mass = Σ Volume × 7850 kg/m³; bar linear

mass check W = d²/162 × L (d in mm, W in kg/m — universal steel geometry, 7850 kg/m³). Add laps (§3.5) as a visible extra row.

  1. Ratio-backed estimate: member volume × assumed steel ratio, declared per element

type:

Elementkg per m³ concrete≈ ratio [practice]
Strip/isolated footings40–700.5–0.9 %
Raft / Bodenplatte70–1200.9–1.5 %
Suspended slabs80–1101.0–1.4 %
Beams110–1401.4–1.8 %
Columns/walls (RC)120–2001.5–2.5 %
Retaining/basement walls100–160—

A tonnage derived from route 2 is an assumption, not a BBS (Stahlliste). A real BBS comes from the stamped structural design; nominal concrete cover bn per DIN EN 1992-1-1 / DIN 1045-1 (exposure-class driven — typically 20 mm slabs interior, 30–40 mm beams/columns [practice]) and lap-splice lengths (≥ 40–65 × bar Ø depending on concrete, coverage and bar Ø) change tonnage by ±15 % more easily than any ratio here.

Cross-check against a primary source (Zahlentafeln für den Baubetrieb, 10th ed. 2024, Tab. 12.18, p.907–908) — the table above is planning-grade practice; the primary source gives wider bands and, for slabs and columns specifically, a materially different picture, so use both and understand why they diverge before quoting a single number:

Element (source terms)kg per m³ concretekg per m² (where given)
Fundamente (footings, generic)25–60 (mean 40)—
Bodenplatten (ground-bearing slab-on-grade)25–355–7 kg/m²
Geschosswände (storey walls, normal)15–203–4 kg/m²
Geschosswände, größere Scheiben (larger shear walls)20–30—
Stützen (columns)100–800 (mean 300–400)—
Decken (suspended slabs, generic)37–454.5–6.5 kg/m² (3–6 m span → 12–20 cm thick, 4.0–9.5 kg/m² depending on Trennwände)
Skelettbau office plate-beam decks115–130— (by 5×5 / 7.5×5 / 7.5×7.5 m grid)
Whole-building average, Mauerwerksbau30–552–5 kg/m³ BRI
Whole-building average, Stahlbetonskelettbau office80–908–10 kg/m³ BRI

Read the divergences as terminology and scope, not error: this file's "Raft / Bodenplatte" (70–120) means a load-bearing mat foundation carrying full building loads, while the source's "Bodenplatten" (25–35) means a simple ground-bearing slab-on-grade — confirm which one the drawing actually is before picking a row. The columns spread (100–800, mean 300–400 vs. this file's 120–200) is real and large: small, highly-loaded columns (upper floors of tall frames, transfer columns) run far above typical wall-like RC columns — never apply one flat column ratio across a whole building; bucket columns by utilisation before ratio-costing them. Suspended slabs also diverge (37–45 kg/m³ vs. 80–110) — likely a span/loading-class difference (source figures skew toward lighter residential/office spans); use the source's span/thickness sub-table when the actual span is known, and this file's higher band as the conservative default when it isn't.

Concrete-demand ratio, whole-building level (same source, Tab. 12.17, p.907) — an early-plausibility check against §3.3's per-m² BGF bands, driven off enclosed volume (BRI) instead: Wohnungsbau (masonry walls + concrete slabs) 0.05–0.08 m³ concrete/m³ BRI; Skelettbau (RC frame) 0.06–0.12 m³/m³ BRI (0.07–0.09 for 5.0–7.5 m spans specifically). Run this alongside §4.2's model takeoff as a sanity bound before trusting a BIM-derived concrete volume — a model result outside this band by more than the span/type explanation above warrants a double-count check (§4.4) before it goes into an estimate.

4.3a Masonry material quantities (stones + mortar per m²)

[Zahlentafeln für den Baubetrieb, 10th ed. 2024, Tab. 12.19, p.908–909 — a full stones-per-m² and mortar-litres-per-m² grid by block format (DF…20 DF) and wall thickness (11.5–36.5 cm); one representative row below, pull the full grid from the source for a real BOQ.]

Format / thicknessSteine/m²Mörtel l/m²Steine/m³Mörtel l/m³
2DF, d = 24 cm6650273200

Explicit waste/allowance factors to apply on top of the geometric quantity: +2–4 % stone quantity for gegliederte Wände (broken-up wall geometry — returns, piers, offsets multiply cut losses); mortar quantity −40 % for unvermörtelte Stoßfugen (dry-jointed perpend joints, common with modern thin-bed/tongue-and-groove block systems); mortar +25 % if Grifftaschen (hand-grip pockets in large-format blocks) are mortar-filled rather than left void. A FreeCAD masonry BOQ that skips these three adjustments will be systematically wrong in a predictable direction — apply them as a percentage step on the raw geometric count, not as a vague contingency line.

4.4 The double-count traps (model version)

  1. Beam–slab overlap: either measure beams at full depth and slabs **net of beam

plan area**, or beams at (D − t_slab) and slabs full. Pick one, write it into the script, state it in the notes. Both-full inflates concrete 4–8 %.

  1. Column–beam at joints: column height clear-between-beams, or full height minus

beam volumes — once.

  1. Foundation vs excavation: backfill = excavation − (consumed volume below grade)

− haul-off; never let the same m³ appear as backfill and as disposal.

  1. Wall vs window/door: the opening subtraction must be live (§4.1); a "wall with

holes already cut" plus another deduction row counts twice.

4.5 Reconcile model output before use

  1. Check derived ratios per m² BGF against §3.3 bands
  2. Cross-check at least two elements by hand takeoff (one vertical, one horizontal)
  3. Resolve every Unclassified / KGunset object — unallocated volume is missing money
  4. Export with gross, deductions, net as three visible columns
  5. Never issue a Mengen list from a model that failed steps 1–4

Section 5: Unit Price Buildup (Einheitspreis-Kalkulation, KLR Bau)

This is the core competence the market respects: an EP you can decompose can be negotiated; an EP you can't is just a number.

5.1 The price stack

EKT = Einzelkosten der Teilleistungen
├─ Lohnkosten (crew wage incl. Zuschläge)
├─ Materialkosten/Stoffe (delivered, net of discounts, incl. losses)
├─ Gerätekosten (machine time or apportionment)
├─ Nachunternehmer (NU) (priced-in sub-contract scope)
└─ Sonstige Kosten (SoKo)
+ BGK Baustellengemeinkosten (site overhead, % on EKT by cost type)
+ AGK Allgemeine Geschäftskosten (head-office overhead)
+ G Gewinn (profit — per KLR Bau 2016 risk "Wagnis" is folded in here, not
a separate element; BGB §650c still uses the older wording [VERIFY])
────────────────────────────────
= Angebotspreis netto
+ USt 19 % [DE; AT/CH different] → brutto

Skonto (cash discount) and Nachlass (negotiated reduction) sit after the price stack and are economically different: 3 % Skonto for paying in 10 instead of 30 days is 3·360/20 ≈ 54 % p.a. — never pay it unless the maths says yes.

5.2 Labour (Löhne)

  • Construction wage cost = Tariflohn (Lohngruppen of the collective agreement) + Bau-

zuschläge + overtime/night/Sunday/holiday premiums.

  • Lohnzusatzkosten (social-wage surcharge): 80–100 % on the Grundlohn

(Zahlentafeln für den Baubetrieb, 10th ed. 2024, p.824 — confirms and widens the earlier 85–95 % digest; treat 85–95 % as the typical band and 80–100 % as the full Bundesland/company-dependent range) — sickness, weather downtime, holiday/ALT levy mechanics. Charge it on productive hours of actual working days. Worked anchors: 85 % (2009 example), 87 % (2020 example, §5.2 below).

  • Lohnnebenkosten per §7 BRTV-type rules (travel/meal allowances) are a further charge

line for workers away from home.

  • Symbols convention: A base → AS +Lohnzusatzkosten → ASL +Lohnnebenkosten →

AP/APS/APSL +Polier (foreman) share.

  • Mittellohn: because you cannot know the exact crew mix at tender time, price the

weighted average hourly cost of the planned crew. Distinguish:

  • Lohn ASL — bare crew average,
  • Kalkulationslohn — average loaded with overhead and profit so the job recovers its

Schlüsselkosten. Never compare these two numbers across offers without knowing which one is quoted.

  • Corrected worked example (Zahlentafeln für den Baubetrieb, 10th ed. 2024,

p.868–869 — Projekt "16 Einfamilienhäuser Bayernallee," Stand 2020, alte Bundesländer — supersedes the earlier ≈34 €/h digest, which undercounted): mittlerer Gesamttarifstundenlohn (blended crew) 20.64 €/h → + 87 % Lohnzusatzkosten → Mittellohn APS 38.60 €/h → + 0.42 €/h Lohnnebenkosten → Mittellohn APSL = 39.02 €/h (final, fully-loaded crew rate). This crew mix skews toward higher Lohngruppen (1 Vorarbeiter, 3 Spezialfacharbeiter, 1 Facharbeiter, 1 Fachwerker, 1 Werker) — treat 39 €/h as a 2020/West-Germany anchor for a similarly senior crew, not a universal constant, and escalate for current wage levels before quoting. Supporting Gesamttarifstundenlohn floor/ceiling by Lohngruppe (ab 1.1.2021, alte Bundesländer, Tab. 12.2, p.822–823): LG6 Werkpolier 24.19 €/h; LG5 Vorarbeiter 22.10 €/h; LG4 Spezialfacharbeiter 21.06 €/h; LG4 Baumaschinenführer 21.40 €/h; LG3 Facharbeiter 19.27 €/h; LG2a 18.78 €/h; Mindestlohn LG2 (ab 1.5.2021) 15.70 €/h; LG1 12.85 €/h.

  • Lohnzusatzkosten range confirmed but wider than stated: the source gives

80–100 % (not 85–95 %) depending on Bundesland/company, with worked examples at 85 % (2009) and 87 % (2020, above) — widen the planning band to 80–100 % and treat 85–95 % as the typical, not the full, range.

  • Aufwandswerte (man-hour values) anchor durations and crew prices — digested BAS-style

bands [VERIFY per current table collection]:

TaskMan-hours
Wall formwork (system)0.2 – 1.0 h/m² (conventional up to 1.2; framed 0.3–0.6; large-panel 0.2–0.5)
Slab formwork ≤ 25 cm0.40 – 1.0 h/m²
Column formwork0.9 – 1.8 h/m²
Rebar placingfootings 8–21, slabs 9–25, walls 12–27, beams 14–28, columns 15–30 h/t (finer bar → higher)
Cutting/bending in the shopØ<10: 9–11; 10–20: 6–8; >20: 4–6 h/t
Concrete placing (pump)0.3 – 0.8 h/m³; +≈ 25 % if skip via tower crane
Excavator trench4 – 20 m³/h sustained

Values scatter strongly with site, crew and weather — validate against your own Nachkalkulation data, and treat any contractor who claims half these values as either brilliant or wrong.

5.3 Equipment (Geräte)

Machine hour/month cost = Kapitaldienst + Instandhaltung (BGL-style logic; price basis of published lists drifts — re-verify current edition before quoting):

  • Linear depreciation a = A / v (A = mean new price, v = Vorhaltemonate planned)
  • Imputed interest 6.5 % p.a. fixed by the costing rules regardless of market

[VERIFY current value]

  • Repairs split 30 % maintenance / 70 % repair; cost types ≈ 60 % labour (no social

surcharges) / 40 % material

  • Time units: 1 Vorhaltetag = 8 h; 1 Vorhaltemonat = 30 calendar days = **170

Vorhaltestunden**

  • Standstill (Stillliegezeit): first 10 days full A + V + repairs; from day 11: 75 % of

A+V plus 8 % maintenance, repairs dropped

  • Operators → Lohn group; fuels, transport, assembly/dismantling → SoKo or device rate
  • Same machine can be EKT (excavator inside an earthworks position) or BGK (tower

crane covering the whole shell phase) — decide per job, don't price it twice

5.4 Material (Stoffe)

Material cost = purchase price after discounts + freight to site + offloading + cutting/scatter/break losses (the §3.5 wastage). Small consumables (nails, tie wires — Hilfsstoffe) go to site overhead, not EKT.

5.5 Gemeinkostenzuschläge — the worked digested example (retaining wall)

Predetermined mark-ups applied to EKT by cost type:

EKT typeGK-ZuschlagFactor
Material + Geräte18.65 %1.1865
Lohn40.12 %1.4012
SoKo17.60 %1.1760
NU15.50 %1.1550

Position example — wall concrete (Wandbeton), EP 133.65 €/m³ @ 120 m³:

Lohn 0.70 h × 34.07 €/h = 23.85 € (× 87.25 % BGK on Lohn variant → 34.80 total GK)
Gerät 10.00 € = 10.00 € (× 1.1865)
Material 65.00 € = 65.00 € (× 1.1865)
GK portion (BGK) = 34.80 €
──────────────────────────────────────────────────
EP netto = 133.65 €/m³ → GP = EP × Menge

(The surcharge set on this position differs from the retaining-wall table above — the point is the mechanic: type-specific factors, visible buildup.)

5.6 Two calculation methods — and the p → p′ conversion

  1. Verfahren mit vorbestimmten Zuschlägen (pre-set mark-ups): EKT × factor per type;

fast; fits simple shell and most fit-out/Technik jobs.

  1. Verfahren über die Angebotsendsumme (project-specific overhead): build the real

BGK for this job from duration and site set-up, then push AGK + profit onto the final sum:

p = (AGK% + G%) of Angebotsendsumme e.g. 7 % + 5 % = 12 %
p′ = p · 100 / (100 − p) auf Herstellkosten e.g. 12 → 13.64 % (NU-only: 10 → 11.11 %)

Schlüsselkosten logic: the overhead not directly attributable to positions (= Angebotssumme − EKT) must be recovered somewhere. Pre-allocate factors on material/device/SoKo/NU, and push the residual onto labour — this is why the Kalkulationslohn (the same logic that pushed §5.2's worked Mittellohn from 20.64 €/h base to 39.02 €/h fully loaded, p.868–869) can run well above the Lohn ASL Mittellohn it started from. Consequence: on a job with reduced labour share, the same absolute overhead costs you more per unit — the reason low-concrete, high-NU jobs must be re-loaded, not copy-priced.

Digested lesson from the same job: the pre-set-mark-up variant understated the project's real BGK by ≈ 20 k€ (126 k vs 147 k) — method check essential, especially for duration-sensitive shell work.

Closing sheet (Schlussblatt) of the digested offer:

EKT 99,006.90 €
BGK 30,695.40 € (Einrichten 7,495 L + 2,500 G + standby 1,500
+ site mgmt 13,800 + operating 2,400 + AV 3,000)
Herstellkosten 129,702.30 €
AGK 7 % + G 5 % (→ p′ 13.64 % auf HK) 17,144.91 € (NU parts 3 % only)
Angebotssumme netto ≈ 146,847 € (+19 % USt)

5.7 Deckungsbeitrag & price floors

DB = Erlöse − variable Kosten. A marginal bid that only covers variable costs can be rational only if the job finishes within the fiscal year and fills otherwise idle capacity — construction firms typically cross their fixed-cost break-even only in Q4. Liquiditätsuntergrenze (short-term floor): profit can go to 0 and A+V on owned devices can be dropped for short jobs; below that you are financing the client.

5.8 Universal physical constants for buildup (transferable)

ItemValue
Concrete wet→dry volume factor× 1.52–1.57 (use 1.54 for mortar-free estimating)
Mortar wet→dry factor× 1.27–1.33 (use 1.30)
Steel density7,850 kg/m³; bar mass W = d²/162 kg/m
Concrete unit weight (RC, for transport/crane)25 kN/m³ ≈ 2,500 kg/m³
Fresh concrete lateral pressureDIN 18218 logic, γ = 25 kN/m³, rise ≤ 7 m/h
Excavated soil swellfS ≈ 1.1–1.3 (loose vs bank); compaction factor fV < 1
Water demand M20-class≈ 160–200 l/m³ (admixture-dependent)
Binder content guide [practice]XC2-class slab/footing ≈ 280–340 kg/m³; C30/37+ design mix via ready-mix; exposure class (DIN EN 206: X0/XC/XF/XA/XS) governs minimum, not habit

Section 6: VOB/C — ATV Numbering, Nebenleistungen, Aufmaß

6.1 What VOB/C is for cost people

VOB/C (ATV — Allgemeine Vertragsbedingungen für Bauleistungen) per trade defines how to build and, in its section 5 "Abrechnung", how it is measured and paid. Ignoring it is both a defect and a billing error.

  • DIN 18299 = the general ATV, always applies where a trade-specific ATV is silent

(special prevails). Structure of every ATV: 0 Hinweise (not contract) · 1 Geltungsbereich · 2 Stoffe/Bauteile · 3 Ausführung · 4 Neben-/Besondere Leistungen · 5 Abrechnung/Aufmaß.

  • Trade ATVs run DIN 183xx–184xx. Numbering relevant to a house estimate

(per digested index — confirm current list):

ATVTradeATVTrade
18299general rules18352tiles/slabs
18300earthworks (Erdbau)18353screed
18330masonry (Mauerwerk)18355joinery/cabinets (Tischler)
18331concrete works (Beton)18356parquet
18332natural stone masonry18357sanitary fittings
18334carpentry/timber18358shutters
18335steelwork18360metalwork (Metallbau)
18336waterproofing (Abdichtungen)18361glazing
18338/18339roofwork / sheet metal18363painting & coating
18340drywall18365floorcoverings
18345composite insulation (WDVS)18366wallcoverings
18349concrete restoration18379–18386HVAC, heating, water/gas, electrical, lifts, automation
18350plaster18451scaffolding

6.2 Nebenleistungen vs Besondere Leistungen — where "all incl." really ends

  • Nebenleistungen (ATV §4.1): trivial extras paid inside the EP — offcuts,

fixing at position, scaffold-level work up to stated height, cleaning.

  • Besondere Leistungen (ATV §4.2): only paid if tendered as their own position

(or provably ordered): extended scaffold times, special formwork, shop drawings, mock-ups (Probeflächen), maintenance handover, extra shifts.

The most expensive tenders are won by bidders who did price §4.2 items the client assumed were "included", then refuses bidders who silently left them out. Audit any offer for the §4.2 list of the relevant ATVs — it is a standardisation cheat-sheet.

6.3 Aufmaß, Leistungsmeldung, Rechnung

  • Aufmaß = the joint dimensional record (or verifiable unilateral with agreed

tolerance); it is the only quantity that gets paid. Common units per ATV: m³ (concrete, earth), m² (wall, floor, façade, formwork as contact area), m (skirtings, pipes, rails), St/No. (fixtures, openings sets), t (steel), Psch/Hz (lump/hour).

  • Leistungsmeldung (progress report for Abschlagsrechnung): measured quantities ×

EP + agreed claims + approved hourly work (Stundenlohn, needs prior agreement — the §2(10) VOB/B rule; deemed-approval fictions are AGB-fragile [VERIFY current case law]); partially done positions at completion %; material-on-site claimable reduced by the cost of installing it; minus deductions.

  • Schlussrechnung must be prüfbar (§14 VOB/B): follows the LV structure, attach

Aufmaß and amount computations, highlight Nachträge. The client's Prüfungsfrist (typically 30/60 d) runs from receipt of a prüfbare bill; objections raised too late kill the withholding defence.

  • Quantity deviations §2(3) VOB/B (unit-price contract) — the four-case logic:
  • ±10 % band: contract EP unchanged (AN's risk / AG's benefit).
  • Qty < 90 %: AN may demand EP increase — lost BGK/AGK/G re-spread over smaller qty

(unless duration shortened).

  • Qty > 110 %: up to 110 % at contract EP; above, new EP with cost saving typically

passed on (no capacity strain) unless AG forced acceleration (§2(5)).

  • Offset over/under-recovered Schlüsselkosten across positions at final account —

agree a global re-spread ("in anderer Weise") to avoid position-by-position repricing.


Section 7: Benchmarks & Plausibility — Derive, Don't Copy

7.1 The copying problem

There is no digested, current, defensible €/m² benchmark table for building types in this skill — published national index values drift by region, price year and scope definition, and copying a rate from another country (or an older handbook) into a live estimate is the classic failure (Section 13). What transfers is the derivation method:

7.2 How to derive local unit-rate benchmarks

  1. Nachkalkulation database: every completed job, roll final costs (Kostenfeststellung

per KG 300/400) ÷ BGF and ÷ BRI → your own €/m² and €/m³ bands per building type. Two comparable projects beat any published table.

  1. Normalise before comparing — for each figure, force: price year + index adjustment,

net vs gross, which KGs included (Baukosten vs +NK vs +Grundstück), BGF definition, storeys/GB-Klasse, spec tier. Never compare lump sums; only normalised rates.

  1. Bottom-up floor from unit prices: KG 320+330+350+360 of a plain shell ÷ BGF gives

the structural €/m² your market can actually produce; benchmarks below that floor are scope errors, not savings.

  1. **Developer-side cross-check (illustrative parameters from a worked valuation model,

not a benchmark):** construction + side costs ~2,000 €/m² BGF assumed, +14 % "Unvorhersehbares" on total investment, rents and yields per local market — use the residual method only to sanity-test order of magnitude. [VERIFY scope]

  1. Tolerance expectations per stage (Section 1.4) — a benchmark ±25 % against your

Kostenberechnung at LPH 3 is not news; the same at LPH 7 is an emergency.

7.3 Plausibility toolkit (bid & cost control)

CheckRule / bandSource of confidence
Leitpositionen≈ 20 % of LV positions carry ≈ 80 % of the bid sum — the planner must personally verify the Aufwandswerte of exactly thosedigested method
TGA shareKG 400 ≈ 25–35 % of gross construction cost (high-tech builds beyond)digested example + method
Hülle + Ausbau ≈ Rohbaumodern-cost trend: façade/fit-out ≈ shell costdigested observation
Site power≈ 0.6 % of build costdigested
Schalung≈ 25 % of shell RC worksdigested (region-specific)
Rebar ratio§4.3 kg/m³ bands; whole-building kg/m² BGF (§3.3)[practice]
Concrete ratio0.35–0.55 m³/m² BGF compact residential RC frame[practice]
Labour/equipment mixKalkulationslohn vs Mittellohn disclosure (§5.2)digested
Wage loadingany Lohnansatz below tariff + 85 % social surcharge → probe itdigested
Waste logisticsconstruction/demolition ≈ >1/3 of EU waste streams; disposal is a real linedigested context

Unusually low bids: public clients have a statutory clarification duty (§16d VOB/A / §60 VgV-type) — and so should you. The bidder must prove the price works; a bid 15–20 % under the reference line without an explanation is an unpaid change-order generator.


Section 8: Tendering & Offer Comparison (Bieterpreisspiegel)

8.1 What must be in the tender pack

  1. LV (Leistungsverzeichnis) — positions with §6.2 §4.2 completeness, units per ATV
  2. Approved/execution drawings (revision-numbered) handed to bidders
  3. Rahmen-/Terminplan with milestones; BE (site setup) responsibilities split
  4. Vertragsbedingungen: VOB/B adopted whole or not at all (partial adoption loses the

AGB-privilege — clause-by-clause review applies [VERIFY case law])

  1. Bindefrist (binding period) — state it; late award past it shifts Bauzeit and price
  2. Urkalkulation submission (public: often required/deposit; private: demand it — see 8.3)

8.2 Pre-award bidder checklist (from the digested risk-screen)

Screen every tender for: payment/billing modalities; Vertragsstrafen (LDs — 0.3 %/AT over completion date with 5 % cap is the admissible pattern, 0.5 % invalid [VERIFY current case law]); Sicherheitseinbehalte; deletion of VOB/B clauses; §4.2 Besondere Leistungen inclusion; shop-drawing delivery duties; local site conditions. Ask clarifications before bidding (Bieterprüfungspflicht — silence can be priced against you).

8.3 Bieterpreisspiegel structure

| Pos | Beschreibung (ATV) | Einheit | Menge | FH | BIeter A | B | C | Min | Δ zum Min % | Referenz (eigene KV) | Δ % zur Ref |
|-----|-----------------------------|---------|-------|-----|----------|---|---|-----|-------------|----------------------|-------------|
| 330.01 | WDVS 16 cm, inkl. §4.2 … | m² | 820 | 1-2 | 96.40 |… |… | 92.10 | 4.7 % | 94.00 | −2.7 % |
| ... (Leitpositionen first — top 20 % by value, ~80 % of sum, §7.3)
| | SUMME Netto (LV) | | | | 512,300 |… |… | | | 505,000 | |
| | Nachlässe % / Skonto | | | | 2 / 3-10 |… |… | | | | |
| | Angebotssumme netto | | | | | | | | | | |
| | Bindefrist / Nebenangebote | | | | yes/no | | | | | | |

Evaluation discipline:

  • Compare position-wise first, total last — a "cheapest" total with 30 % overpriced

early positions is a front-loaded cashflow trap (compare each position's % of total against your Kostenberechnung distribution).

  • Row minima alone don't award; award to the economically most advantageous offer

(quality/term/price criteria published in advance; for public: net price basis).

  • Deviation bands for a residential shell: ±7 % normal spread; +8–15 % itemise

and negotiate; > +15 % retender; −8…−15 % check exclusions/spec cuts; < −15 % red flag → missing scope or claim-driven bidding. [practice thresholds]

  • Insist on the Urkalkulation of the intended winner for the Leitpositionen — it

stops speculative pricing and is your defence line for §2(5)/(6) and §650c BGB change-order valuation ("Herkunft der Preisformation").

8.4 Payment, retention, securities (contractor-economics literacy)

InstrumentBasisPractical value
Vorauszahlung (advance, e.g. long-lead material)§16(2) VOB/Bsecure it (bank guarantee)
Abschlagszahlung§16(1) VOB/B / §632a BGB; due 21 d after prüfbare Aufstellungpay against Leistungsmeldung + Aufmaß only
Schlusszahlung≤ 60 d after receipt (§16(3))hold Prüfungsfrist discipline
Default§286 BGB: 30 d after invoice+due; interest +9 pp above base rate (B2B)date everything
Vertragserfüllungssicherheit≤ 5 % of award (old §9c VOB/A numbering [VERIFY current])guarantee preferred over retention
Mängelansprüche-Sicherheit≤ 3 % of final account; retention max ~10 % total; client deposits into Sperrkonto within 18 Werktage; interest to contractoror release against guarantee
Aval fee0.5–1.0 % p.a. of sum — consumes credit linecheaper than long retention
Verbraucherbauvertrag (private client)Abschläge ≤ 90 %; first payment needs 5 % performance security; Baubeschreibung + Widerrufsbelehrungmandatory on consumer builds

Section 9: Reserve (Contingency), Allowances & Escalation

9.1 Reserve by design maturity

Stage / conditionReserveRationale
Konzept / Kostenüberschlag20–25 %scope itself uncertain
Vorplanung / Kostenschätzung15–20 %quantities ±20 %
Entwurfsplanung / Kostenberechnung10–15 %most details unresolved
Execution drawings + known site + tenders in5–10 %new-build standard
Complete docs + firm prices + documented site3–5 %floor — never below 3 %
Retrofit/UMF without as-builts10–25 %hidden conditions; Altlasten risk

Reserve reduces as certainty increases — carry high early and formally release the difference at each stage; do not silently keep 25 % and spend it as profit. DIN 276:2018 shows the Reserve outside the KG sums as its own declared line [VERIFY presentation], so nobody "finds" it inside a position.

9.2 What Reserve does and does not cover

CoversDoes NOT cover (name it separately)
quantity drift within defined scopeclient scope change → Nachtrag (§2(5)/(6), §650b)
minor unforeseen site conditionsmajor ground/contamination risk → risk allowance, often KG 100/200
small rate variationsescalation (§9.4)
coordination gapsrework from design error → professional liability, not the client's pot
weather within normal rangeforce majeure / higher force (contract-specific)

Track drawdown as a visible line: 40 % complete + 80 % of Reserve spent = re-forecast, don't carry on hoping.

9.3 Allowances & PS

TypeUseTreatment
Provisorische Position / PSscope defined, spec open (kitchen, FA-Branding)carry at face value; reconcile at actuals
PO (Posten mit Unbestimmter Anzahl / loose-sum item)decision pending (Ausbau, lighting)state it; overrun is client's
Stundenlohnarbeitsmall undefined extrascap it; requires prior agreement, hourly sheets within days

9.4 Escalation (price adjustment)

A separate line from Reserve, sized on the material-weighted part of cost over the programme midpoint:

Escalation ≈ Base cost × material share (~0.5–0.6 construction cost)
× expected p.a. build-price index × (duration_years / 2)
ProgrammeTypical allowance [practice]
≤ 6 months1–3 %
9–12 months3–5 %
15–24 months6–9 % — and/or a price-adjustment clause (Stoffpreisgleitklausel logic for public work)
> 24 months10 %+ plus indexed contracts

Hedge: early procurement/lock-in of the two most volatile bulk goods (cement-class materials, steel) often beats carrying the allowance — cost the decision (storage, working capital, deterioration) explicitly.


Section 10: HOAI — Architects' & Engineers' Fees

10.1 Status

HOAI is (since 2021, after the ECJ ruling) orientation, not price law — fees are freely negotiable. Without any fee agreement, statutory minimum rates historically apply (irrefutable §7(5) mechanism [VERIFY post-2021 effect]); always put the fee, Leistungsbild, zone and anrechenbare Kosten in writing at award.

10.2 The nine Leistungspflichten (LPH) and phase weights

1 Grundlagenermittlung · 2 Vorplanung · 3 Entwurfsplanung · 4 Genehmigungsplanung · 5 Ausführungsplanung · 6 Vergabevorbereitung · 7 Mitwirkung bei der Vergabe · 8 Objektüberwachung · 9 Objektbetreuung/Dokumentation

Phase weights for Objektplanung Gebäude (HOAI-2013 table, % of full fee — sums 100):

LPH123456789
%2715325104322

Other disciplines have different distributions (IngBauwerke weight LPH 2–3 much higher, Tragwerk LPH 5 heavy) — [VERIFY each column against current HOAI annexes before use]. Cost truth: ≈ 54 % of the fee is spent by end LPH 5 while ≈ 80–90 % of construction cost decisions are locked by LPH 3 — which is exactly why cost work concentrates there.

10.3 Fee buildup — five steps (worked digested example)

1 anrechenbare Kosten (net) infill 3-storey building: KG300 800k + KG400 200k = 1.0 M€
(TGA fully countable at exactly 25 % share of construction cost — see 1.3)
2 Honorarzone per Merkmalskatalog 34 pts → HZ IV
3 Grundhonorar from degressive table: HZ IV @ 1.0 M€ → min 144,268 € / max 162,464 €;
Mittelsatz = (144,268+162,464)/2 = 153,366 €
4 × phase share: LPH 1–4 = 2+7+15+3 = 27 % → 153,366 × 0.27 = 41,408.82 €
5 + Zuschläge (Umbau +20 % default presumption on mvB; AHO category method up to ≈ 33 %
for HZ I–III [VERIFY current AHO wording]) + Nebenkosten (expenses) + VAT

Zone corridors per the digested catalogue: 6–8 → I, 14–16 → II, 22–28 → III, 34–36 → IV, 42 → V (criteria: Einbindung, Funktionen, Gestaltung, Konstruktion, techn. Ausrüstung, Ausbau, each 1–9) [VERIFY against §35 HOAI]. Table ceilings: Gebäude/Tragwerk/Verkehr 25/15/25 M€, TGA 4 M€, Freianlagen 1.5 M€; above → free negotiation (extended degressive tables exist to ~500 M€ by agreement).

10.4 Cost-side rules of thumb

  • Fee for Besondere Leistungen (extra reports, certification coordination, BIM management

beyond standard) and for services outside the tables (Brandschutz, SiGeKo, Projektsteuerung per AHO, Gutachten) is free — quote and contract separately.

  • Multiple similar objects: separate fees; essentially-same objects get repeated-phase

reductions (≈ 50 % LP1–6 for the 1st–4th, 60 % 5th–7th, 90 % beyond) [VERIFY].

  • Fee falls due at Abnahme + prüfbare Honorarschlussrechnung; time charges (no more

HOAI hourly rates — internal cost rates): digested office example ≈ 106 €/h for a 12-y project engineer using gross-salary × 2.5–3.0 overhead factors.

  • A fee agreement is void if it misses: correct Leistungsbild, anrechenbare Kosten per

DIN 276, zone, rate, performed services, surcharges/deductions.

  • §650p BGB Zielfindungsphase (A/I contracts): if goals are essential-undefined, the

planner first owes a basis + cost estimate for a fee — the anti free-pitch rule; relevant whenever you are asked for "just a quick number" before contract.


Section 11: Life-Cycle Cost (LCC)

11.1 The share logic

Herstellung (KG 200–700) << Nutzung (Betrieb + Instandhaltung über 30–80 a)
  • Greenhouse-gas analogue: offices ≈ 75 % of lifecycle GHG is operation; residential

≈ 60–2/3 — and falling as grids decarbonise, which flips the problem toward grauE Emissionen (embodied). [VERIFY shares; dated studies]

  • Cost analogue from the digested literature: **operating costs equal the purchase

(construction) cost after roughly 7 years — a 50-year building therefore carries an order of magnitude more operating than construction cost (assumption-dependent; tag dated). The planning consequence: decisions that shift 5 % construction cost but 15 % operating cost are construction-cheap and LCC-expensive.**

  • LCC rail: DIN 276:2018 cost groups (esp. 300/400) + DIN 18960 Nutzungskosten (Energie,

Wasser/Abwasser, Reinigung) + Inspektion/Wartung/Instandsetzung per DIN 31051 terms (Wartung ≠ Instandsetzung ≠ Verbesserung/Modernisierung).

11.2 Static cost comparison (the digested floor-covering method)

40-year horizon, 2 % interest, annuity-style (kalk. Abschreibung + half-interest + cyclic maintenance + cleaning 5–6 €/m²·a):

CoveringInvest € /m²Nutzungsdauer aCyclic costs€/m²·a over 40 a
Carpet1010—6.10
Parquet6040seal 8 €/m²/10 a; sand 20 €/m²/20 a9.20
Natural stone8060joints 15 €/m²/20 a9.78

Reading: the 6× cheaper carpet is only ~30 % cheaper per year — and that ignores replacement disruption. Always compare variants on the annualised column, never the investment row. Extend to building systems: heat-pump vs district-heat vs PV combos; complexity (Performance Gap: installed systems underperform) counts as a cost, not a spec.

11.3 Maintenance intervals & lifetimes (per system, digested)

SystemUse life / interval [VERIFY, dated sources]
Building cycle (refurbishment trigger)50–80 a; structure far longer, TGA far shorter
TGA in stock≈ 30 a cycle → two TGA lifetimes per shell lifetime — plan access & exchange routes
Windows40–50 a frames; gasket/hardware/glazing shorter; repair vs replace per condition
WDVS40–60 a; < 10 a if defective/unmaintained — coating cycles are the lever
Anchors/adhesives in façadesplan 25 a → 2 cycles over 50 a doubles CO₂ and cost of that layer
Clay/brick masonry100–150 a; 94 % re-use/recycling paths exist
Vented/rainscreen façadesVDI 6200: owner walk-by 2–3 a, expert inspection 4–5 a, full review 12–15 a
PVenergy payback vs 25–30 a life; yield up to ~20× production energy over life
Maintenance strategyDIN 31051 (Inspect/Wartung/Instandsetzen/Verbessern); design maintenance access — complex systems avoid

11.4 Green premium — what's actually evidenced

  • The premium sits in rent and asset value: offices ≈ +6–8 % rent / +14–16 % asset

value in the digested survey (dated). For residential construction cost, the digested material gives no evidence of a systematic green premium — and the low-tech/sufficiency findings point the other way (reduced complexity and comfort-standard trimming save ≈ 10 % construction cost in the Gebäudetyp-E logic). Plan sustainability with LCC arithmetic, not with premium folklore.

  • Carbon pricing for the calculation side: national levy 45 €/t CO₂e (2024, dated); UBA

shadow price 237 €/t CO₂e (purchasing-power 2022; intergenerational-weighted variants 809–860 €/t); one state mandates ~250 €/t in LCA for public builds [VERIFY current values/regions]. EPBD path: mandatory lifecycle-GWP reporting for new buildings > 1,000 m² users from 2028, all new from 2030 — an eLCA-style calculation is becoming a deliverable adjacent to the Kostenberechnung; model quantities (Section 4) are its input.


Section 12: Worked Examples

12.1 Model → estimate pipeline (compact residential, illustrative)

Scope: 4-storey RC-frame residential, BGF 1,450 m², BRI 4,200 m³, standard spec, LPH 3.

Takeoff (model, §4 logic; net = gross − visible deductions):

KGPosition (ATV)UnitGrossDeductNet
310excavation incl. shoring allowance (18300)m³860— (loose factor in haul-off line)860
320blinding 8 cm (18331)m³34034
320foundation slab 30 cm C25/30 XC2 (18331)m³1522150
320footings/stripsm³96096
340interior walls RC/stonem³18814 (open. > thr.)174
330exterior walls masonry + WDVS carrierm³20531174
350slabs 20 cm (18331, net of beam overlap — method stated)m³2908282
360flat roof structure incl. fallsm²3906384
—RC total (320+340+350)702 m³ → 0.48 m³/m² BGF ✔ (§3.3 band)
—rebar (ratios §4.3: slab 95, wall 150, footing 55)t≈ 58 t → 40 kg/m² BGF ✔
400TGA allowances (410–480, benchmarked)PSch——sized to 28 % of KG 300+400 (§7.3 band)

Pricing with §5 mechanics (local price level placeholders — replace every unit rate from your own data before use):

Example EP, slab concrete C25/30 pump (18331):
Lohn 0.55 h × 42 €/h (KalkLohn local) = 23.10
Gerät 1.20 € + Material 78 € = 79.20
EKT = 102.30 × GK(≈ 20/40 % split) → ≈ 124 €
AGK+G via p′ (12 % → 13.64 % auf HK) ≈ +16.9 €
EP ≈ 141 €/m³ → GP = 282 m³ × 141 ≈ 39.7 k€

Roll all positions → KG 300 ≈ (illustrative) X; KG 400 ≈ 0.28·(X+Y); KG 200 + 500 + 600 per scope list; KG 700 from Section 10; Reserve per §9.1; output on the §14.2 sheet.

Plausibility exit: total ÷ BGF compared only against §7.2-derived local bands; triangulation (§2.3) A/B/C within 10 % or investigate.

12.2 Unit price with overhead push-down (the digested retaining wall)

Already built line-by-line in §5.5/§5.6: EKT → GK by type → Herstellkosten → project BGK table → p′ conversion → Angebotsendsumme. Use the Schlussblatt skeleton for any bid:

Positions-EKT by type (Lohn / Stoff+Gerät / SoKo / NU)
+ BGK: Einrichten/Räumen · Vorhaltekosten(duration × monthly standby) · örtliche
Bauleitung · Betrieb · technische Bearbeitung ← time-dependent items = duration
+ = Herstellkosten
+ AGK+G (as p′, or project-derived for long jobs)
+ Wagnis considerations inside G; Skonto/Nachlass at end
= Angebot netto → + USt

If the bid is won on labour-pushed rates, keep the Urkalkulation — every later Nachtrag (§650c BGB: actual necessary costs + appropriate AGK/W/G surcharges, or continuation from the deposited Urkalkulation) is argued from it.

12.3 HOAI fee (LPH 1–4) — digested example

See §10.3 worked figure: 1.0 M€ anrechenbar → HZ IV → Mittelsatz 153,366 € → LPH 1–4 (27 %) = 41,408.82 € before Zuschläge and VAT. Recompute with the current negotiated rate — the table values are orientation (§10.1).

12.4 Quantity-deviation bill correction (§6.3 mechanics)

Slab concrete contracted 120 m³ @ 133.65 €; as-built 160 m³ (+33.15 %): first 110 % at contract EP; the 33 % surplus portion re-priced with recovered overhead: (0.3315 − 0.10) × 120 × [0.5·34.07·0.8725 + 10·0.1865 + 65·0.1865] ≈ 801 € additional charge in the digested example — i.e. the client captured most of the saving; only the AGK/G tail moved. Same logic, opposite sign, for quantities below 90 %.


Section 13: Failure Patterns

#FailureConsequenceFix
1Benchmark €/m² BGF applied to NF-sized areas (or vice versa)±15–35 % swing; "copy-paste errors" look like planning genius or fraud§3.4: denominator law
2Mixing Kostenermittlungsstufen — "Kostenvoranschlag/Kostenanschlag" used for a Schätzungwrong liability; budget promise you never made§1.4 terminology discipline
3KG mixups: lift in 300 not 460; Fenster in 400; Fassade in 350; Betriebseinrichtung inside "Baukosten"structure unreadable, TGA/facade shares uncheckable§1.2 assign each position one code
4Edition drift (2008 vs 2018 500/600/700) silently mixedtotals non-additivename the edition in the report
5Missing Erschließung (KG 200: Anschlusskosten, Herrichten, Kampfmittel) or treating it as "utility's job"late five-figure surprises§1.2 content list; ask network operators early
6Missing KG 700: HOAI, Prüfstatik, SiGeKo, Vermessung, insurance, interim financing"over budget" though build cost on target§10 costs are a real line
7Copying foreign/city rates (incl. this file's digested € figures)systematic error at local price level§7.2 derive locally
8Beam/slab or wall/window double-count in modelconcrete +4–8 %§4.4; script declares the method
9Gross measured directly as net; deductions invisibleunreproducible estimate§2.2 three-column discipline
10Wastage inside paid Menge / not in procurementcontractor paid for waste, or you run short§3.5 two columns
11Reserve merged with escalation ("7 % misc")unmanageable, unreleasable§9.1/§9.4 separate lines
12§4.2 Besondere Leistungen assumed "all incl."change-order war at Abrechnung§6.2 audit each offer
13Award on position minima alone / unbalanced low bid acceptedrecovery via Nachträge; front-loaded drawdown§8.3
14Paying Abschläge without Aufmaß/Leistungsmeldungno leverage, overpayment§6.3/§8.4
15VOB/B partially adopted/modified "to be safer"AGB control voids the comfort clauses§8.1 whole-or-none
16Kalkulationslohn vs Mittellohn compared across offerswrong winner§5.2
17Net/gross (USt) mixing in anrechenbare Kosten / comparisonsfee & benchmark errors§1.3/§7.2
18Comparing variants on investment row only (carpet vs stone)LCC blindness§11.2 annualise
19TGA designed without maintenance access, lifetime assumed = shell2–3 exchanges you can physically do§11.3
20Stale rates presented as current; no date stampquiet erosion of every %date every basis; §7.2

Section 14: Templates

14.1 BOQ/position line (LV-style)

| Pos | KG | Beschreibung (ATV DIN 18xxx, §4.2 stated) | Einheit | Menge | EP netto | GP netto |
|-----|-----|----------------------------------------------|---------|-------|----------|----------|
| 5.1 | 350 | WBK Decken C25/30, XC2, Pumpen, o. S+B, | m³ | 282 | 141.00 | 39,762 |
| | | inkl. Nebenleistungen gem. DIN 18331/18299 | | | | |

14.2 Kostenberechnung summary sheet

PROJEKT <name> ORT BAUHERR
STAND Kostenberechnung nach DIN 276:2018-12 DATUM / BEARBEITER
BEZOUGSFLÄCHE BGF ___ m² (DIN 277) BRI ___ m³ NF ___ m²
VOM KOSTENTRÄGER KG 100 __ KG 200 __ KG 300 __ KG 400 __
KG 500 __ KG 600 __ KG 700 __ (= Summe Level-2, netto)
RESERVE (DIN 276:2018, outside KG sums) __ % __ €
ESKALATION (Basis: Laufzeit __ Mon., Anteil __ %, Index __ %/a) __ €
= GESAMT (netto) __ € → €/m² BGF __ → €/m³ BRI __
TRIANGULATION A __ € B __ € C __ € max Δ __ %
ANNAHMEN / NICHT ENTHALTEN (Grundstück? Betriebseinrichtung? Möbel?)
HONORAR-BASIS anrechenbar netto (1.3): __ € HZ __ Zone-Quelle __
STATUS: Planungsstand — nicht vergabereif; Preise vom __, fortzuschreiben.

14.3 Offer comparison sheet — see §8.3 block.

14.4 Final checklist before issuing any cost figure

  • [ ] Stage named (1.4) and tolerance honestly stated
  • [ ] Scope label (1.5) + DIN 276 edition + every position one KG
  • [ ] Denominator BGF or NF, DIN 277, printed next to each rate
  • [ ] Gross/deduct/net visible; model export reconciled (§4.5)
  • [ ] Rebar method (BBS vs ratio) disclosed (§4.3)
  • [ ] §4.2 items checked per relevant ATVs (§6.2)
  • [ ] Unit prices decomposable (§5); Kalkulationslohn disclosed
  • [ ] Reserve outside KG sums, escalation separate (§9)
  • [ ] KG 200/700 contents not forgotten (§13 #5/#6)
  • [ ] HOAI anrechenbar net, zone + table source named (§10)
  • [ ] Offers compared position-wise; low outliers probed (§8.3)
  • [ ] Date stamp on rate basis; > 6 months → re-verify

Quick Reference Card

DIN 276:2018 100 Grundstück(110/120/130) 200 Herrichten/Erschließen
300 Baukonstruktion 310–390 400 TGA 410–490
500 Außenanlagen* 600 Ausbau/WE* 700 Baunebenkosten
(*titles/500–700 mapping edition-dependent — VERIFY + name edition)
STAGES Rahmen→Überschlag→Schätzung(LPH2)→Berechnung(LPH3=fee+agreement
basis)→Anschlag(LPH7 tender)→Feststellung tol ±20-30→±3-5%
"Kostenvoranschlag" = OLD word; Reserve OUTSIDE KG sums
AREAS always €/m² BGF or NF (DIN 277) — NF/BGF 0.65-0.80 → rate error!
PRICE STACK EKT(Lohn/Mat/Gerät/NU/SoKo)+BGK+AGK+G =netto; Wagnis in G; +19% USt
LOHN +80-100% Lohnzusatzkosten (typical 85-95%); A/AS/ASL; Mittellohn vs Kalkulationslohn
GERÄT A/v + 6.5% Zins + R(30/70); Monat=170h; idle>10d: 75%A+V
GK example Lohn 40.12% Mat+Ger 18.65% SoKo 17.60% NU 15.50%
METHOD 2 p(AGK+G auf Summe) → p′ = p·100/(100-p) 12% → 13.64% auf HK
Schlüsselkosten residual → push onto Lohn (20/80 Leitpositionen!)
AUFMASS gross→deduct→net; §2(3) VOB/B: ±10% band; <90% EP↑; >110% EP↓;
Schlussrechnung prüfbar §14; Abschlag 21d; Schluss ≤60d; Verzug 30d
Sicherheit: VE 5%, Mängel 3%, Einbehalt ≤10% Sperrkonto 18WT; Aval 0.5-1%/a
MEASURE openings: concrete deduct >0.1 m², masonry both-face >1.5 m² [VERIFY ATV]
concrete 0.35-0.55 m³/m² BGF · rebar slab 80-110 wall 120-200 kg/m³
laps +4-6% ≠ waste 3-5% · Schalung= contact area · pump 0.3-0.8 h/m³
HOAI LPH 1-9 = 2/7/15/3/25/10/4/32/2 % (Gebäude); HZ I-V; degressive table;
anrechenbar NET (110/710/760 excl.); mvB=KKW×ZF×LF; Umbau +20%;
SINCE 2021: negotiable — tables orientation only!
LCC operation >> construction (GHG 60-75% use phase; costs ≈ build cost
after ~7 a); floors: 10€carpet/10a vs 80€stone/60a → 6.1 vs 9.8 €/m²·a;
TGA ~30a < shell 50-80a; windows 40-50a; WDVS 40-60a (defective <10!);
green premium: rents +6-8%/value +14-16% — NO construction-cost premium
proven for residential; CO₂ shadow 237 €/t (UBA), levy 45 €/t(2024)
(dated/VERIFY); eLCA mandatory 2028 >1000 m² / 2030 all (EPBD)
RESERVE concept 20-25% | Vorentwurf 15-20% | Entwurf 10-15% |
complete docs 5-10% | floor 3% | retrofit 10-25%
ESCALATION base × matl-share(~0.55) × index × duration/2 — separate line
AUDIT triangulate A/B/C ≤10% · position-wise compare · <-15% bid = RED FLAG ·
no decomposition = no negotiation · foreign rates NEVER copy
ALWAYS state stage+scope+denominator+price date · separate Reserve/Escalation ·
HOAI anrechenbar NET · say unprompted: planning aid, not binding
Kostenberechnung/Anschlag — signed planner + current-standards check
(DIN 276/VOB/HOAI editions moved!) required before any commitment.