currentAutomated scan100/100name: existing-structures-retrofit description: > Bauen im Bestand (working with existing structures) for DACH practice: condition assessment workflow (Dokumentation, Bestandsaufnahme, Voruntersuchung, Bauwerksprüfung with DIN 1076 cycles — Hauptprüfung 6 a / einfache Prüfung 3 a / Beobachtung, S/D/V Zustandsnote 0–4, RÜV and VDI 6200 CC/RC inspection cadence); material testing (reinforcement induction scan, half-cell potential, phenolphthalein carbonation, chloride profiles, Rebound ≥9 readings, cores per DIN EN 12504/13791 with 5%-fractile statistics), historical concrete/rebar strength lookup tables (W200/Bn/B/TGL/C classes, Betonstahl I–IV fyk, smooth-bar bond caveats); code path (Bestandsschutz grandfathering, Anpassungsverlangen, Nachrechnung DIN 1045-2→EC2 with reduced γM concrete 1.20–1.50 / steel 1.05–1.10 under qualified-inventory conditions, γF permanent −0.25/+1.15); load assumptions for old stock (Mp/m² conversions, historical use loads, snow); utilization re-check worked examples (1975 slab three-stage, slender column 2nd-order); strengthening with numbers (Aufbeton ≥40 mm + joint-shear check with roughness coefficients and dowels, Bewehrungsergänzung, Spritzbeton jackets with confinement gains, CFRP bonded/ slotted λM factors, steel plates, prestress, added bracing walls, foundation underpinning DIN 4123); defect catalog (carbonation dk=α√t, chloride pitting, static vs active cracks, settlement signatures, frost, ASR, sulphate, rising damp); moisture/mould remediation ladder incl. fRsi≥0.7; energy retrofit (GEG component U-limits for owners, WDVS + fire constraints, roof/top-floor/ cellar-ceiling plays, window replacement logic, heat-pump flow-temperature strategy 40–50 °C); LCC economics (operation 60–75% of lifecycle GHG, CRREM, VDI 2067); assess→target→verify→strengthen→monitor sequence with decision tree, failure patterns, verification checklist, and FreeCAD/IFC scan-to-BIM modelling of existing fabric. Practice values flagged [VERIFY] where source tables were lossy; not a statutory substitute for a Tragwerksplaner/Prüfingenieur. metadata: version: "1.0.0"
Existing Structures & Retrofit (Bauen im Bestand) — DACH Practice Skill
Simple-first gate (governs how this skill is applied). Default every choice here tothe simplest proven solution at the agreed standard tier — see the governing skillsimple-first-building(complexity ladder §1). Escalate to more demanding construction(innovative systems, one-off details, higher comfort tiers) only when the clientexplicitly asks for it, with cost/schedule impact stated; deviate below the usualstandard or the aarRdT only via the documented risk-acceptance machinery(simple-first-building§3) — public permission never cures the private default.
Agent-neutral procedure skill for assessing, re-checking and strengthening existing buildings (and for deciding whether to), under the German-language regulatory and normative framework. German terms are kept in parentheses because inventories, Prüfberichte and submissions circulate in German.
Scope. Reinforced concrete / masonry stock of the 20th century is the core (worked examples follow it); timber and steel defect logic is included at assessment level. Bridges/civil works appear only through the inspection machinery (DIN 1076) that building practice borrows. Energy and services retrofit is covered to the interface where the building-physics, TGA and fire skills take over.
0. How to use this skill — and the [VERIFY] convention
Use this skill when the task involves ANY of:
- converting/intensifying use of an existing building (living→office, add-on storey, new
openings),
- re-checking (Nachrechnung / Nachweis im Bestand) old members against current rules,
- planning strengthening (Aufbeton, jackets, CFRP, added walls, underpinning),
- diagnosing defects (cracks, spalling, corrosion, damp, mould, settlement),
- condition survey programmes and inspection cycles for owned/municipal stock,
- deciding retrofit vs. demolish, with whole-life numbers,
- modelling existing fabric (scan-to-BIM) for any of the above.
[VERIFY] convention. This skill is distilled from standards-adjacent references; some source tables arrived lossy. Any figure or rule marked [VERIFY] must be re-read in the current norm text (DIN EN 1990/1992, DIN 1045-2, DIN 1076, VDI 6200, GEG in force at project date) before it goes into a calculation report. Unmarked values are safe to use as planning figures; final design remains the job of a licensed Tragwerksplaner, and re-checks in Germany are coordinated with the Prüfingenieur für Standsicherheit / building authority early.
Hard limits of this skill: it never replaces a Voruntersuchung by qualified persons, never certifies Standsicherheit, and treats pollutant findings as triggers for specialist measurement (Schadstoffkataster), not as clearance.
1. Master sequence: assess → define target → verify → strengthen → monitor
Every Bestand project runs the same five phases; skipping or overlapping them is the root cause of most retrofit failures.
| Phase | German | Output | Typical trap | |
|---|---|---|---|---|
| 1 Assess | Bestandsaufnahme / Voruntersuchung | documented condition + material data + defects + pollutants | building on drawings alone; no cores; no crack mapping | |
| 2 Target | Zieldefinition / Nutzungsänderung | load model, target utilization, residual life, service class | authority/owner expectations not fixed before measuring | |
| 3 Verify | Nachrechnung / Bewertung | utilisation per member, code path (Bestandsschutz vs. new rules) | mixing code generations; ignoring old detailing rules | |
| 4 Strengthen | Ertüchtigung / Instandsetzung | method choice with force-transfer details, staging checks | composite-interface shear forgotten; load-introduction zones | |
| 5 Monitor | Beobachtung / Bauwerksbuch update | gauges, re-inspection cadence, documented as-built change | "repaired and forgotten"; no follow-up cycle |
Stock context that makes this discipline worth it: roughly 10 % of dwellings are younger than 15 a, about 60 % were built before 1960, and of refurbishments only ~25 % are driven by repair need while ~75 % are driven by change of use (Nutzungsänderung). A re-check that cannot prove the existing member under the NEW use will end in strengthening — plan for it.
Vocabulary (DIN EN 1990 / industry usage, keep them apart in reports):
- Instandhaltung — maintenance: preserves the target state (inspect, service).
- Instandsetzung — repair: restores the target state after damage (same design
goals).
- Ertüchtigung — upgrade: raises the target state above the original (new loads,
new code level, strengthening).
- Nachrechnung — re-check: proof of an existing structure under CURRENT rules,
with code-permitted relaxations where the standard allows.
- Bestandsschutz — grandfathering: lawfully-erected fabric may remain even if
today's rules differ (§ 2).
- Nutzungsdauer / Lebensdauer — design working life (DIN EN 1990: 50 a for
buildings, 100 a for monumental/bridge-type structures) vs. actual service life.
- Mischungsverbot — do not mix code sets within one verification; exception:
non-monolithic precast joints transmitting only support forces.
2. Code path: Bestandsschutz, change of use, and the Nachrechnung transition
2.1 Bestandsschutz (grandfathering) — what survives and what breaks it
Principle: a structure lawfully erected and maintained under the rules of its time may remain, even though it would not be approved today. Repairs may follow the old rules. Preconditions, all three:
- original lawfulness (Baugenehmigung, conformity at erection),
- no substantial change (keine wesentliche Änderung),
- condition as intended at erection — normal wear only.
Bestandsschutz is lost where there is danger to life/health, or where the intervention reaches the quality of a new building. Loss also never covers damage that arose from a rule now known to be insufficient (example in the case law tradition: overhead single-pane glazing ESG→VSG must be upgraded even on repair).
Authority levers (MBO logic, adopted into Landesbauordnungen):
- Anpassungsverlangen (§85(1)5 MBO) — authority may demand compliance to
current requirements where a concrete danger exists; burden of proof on the authority. Health-hazardous products (e.g. asbestos in reachable condition) can trigger replacement even of untouched parts.
- Harmonisierungsverlangen — on a substantial change, directly adjacent
constructive-related parts may be pulled up to current rules if no unreasonable extra cost results (e.g. a new stair may pull the adjacent landing and stair enclosure up to current rules).
- Intervention grading (stages A–C): A = renewal of defective parts with same
use, substance not destroyed → procedure-free; C = interventions so deep that a whole-building proof is triggered. Classify the planned work early.
2.2 Change-of-use / alteration rules that drive the statics
- Durchbrüche (new openings): local compensation per CURRENT rules (e.g. RC
frame action); no whole-building current-rule proof triggered by the opening.
- Umbau storey loads: load path of NEW or altered elements per current code;
existing parts may keep the historic verification and merely carry the added loads; any strengthening member is designed to the new code.
- Aufstockung (add-on storey): the added loads per current actions standard
must be carried; unchanged lower parts are proven under the ORIGINAL code including the new loads; if lower storeys would need substantial change anyway, the whole building is treated as a new build.
- Later "neue Erkenntnisse" (corrected old rules) can reopen the historic proof.
- New products (retrofit adhesives, FRP, grouts) always need current conformity
route (CE / abZ / ZiE) — grandfathering never covers them.
2.3 Nachrechnung: existing-code → EC2/DIN EN 1992 transition
Two-stage material assessment is the standard route: (1) derive nominal strengths from documents/historic code tables, (2) upgrade by testing where needed. The transition vocabulary old↔new must be exact in the report:
- σ-Verfahren (working stress) until 1972 in West Germany; **Traglastverfahren
(ultimate load)** introduced in the GDR from 1955 with a global η factor — GDR-era calculations are NOT directly comparable to EC2 utilization.
- 1972 DIN 1045: strength classes Bn50–Bn550 as 5 % fractile 28 d cylinder, design
value = β·Nennwert with global safety η; 1978 units switched N/mm²; 2001/2011 C-classes (EN 206).
- Concrete and steel partial factors may be reduced for the re-check of
existing RC if a qualified inventory exists (§ 4.7 modified γ table and its preconditions). Without qualified inventory, full current factors apply and the tabular historic strengths (§ 4.5) govern.
3. Documentation and survey programme (Bestandsaufnahme)
3.1 Paper/digital records to chase before any drilling
Checklist (as-found documentation set):
- ownership + land survey (Lageplan), permits (Baugenehmigung incl. old annexes),
- as-built statics: structural calculations, reinforcement plans/Barroschauen,
formwork plans, precast connection drawings,
- TGA as-builts, facade/waterproofing documentation, expert reports, test fields,
- utility routes and Kampfmittel (UXO) records, maintenance logs / Bauwerksbuch,
- records of changed actions: groundwater level shifts, adjacent excavations,
- events: fire, storm, flood, mining subsidence, earthquakes,
- alteration history (changes of use, added loads: racks, machines, PV, greening),
- neighbour situation (Beweissicherung — documented adjacent-condition).
Missing records are the normal case for pre-1960 fabric and force the testing route of § 4. The documentation set closes with a Bauwerksbuch-style conformity summary.
3.2 Physical survey methods (selection by question)
| Question | Method | Notes from practice | |
|---|---|---|---|
| rebar position/diameter/cover | induction scanning / cover meter | destructive confirmation on anchorage zones | |
| carbonation depth | phenolphthalein on fresh fracture | uncarbonated = red; carbonated stays colourless below pH≈9 | |
| chloride content | powder from ground profiles, wet chemistry / potentiometric titration | profile vs. depth, not single surface value | |
| corrosion activity | half-cell potential mapping | indications, not quantification | |
| concrete strength | Rebound (Schmidt) and/or cores | Rebound supplementary only; cores per § 4.6 | |
| crack width | calibrated loupe / gauge | map plan + elevation, mark active-crack monitors | |
| crack depth | core or ultrasonic across crack | ||
| voids/laminations masonry | tap test; endoscopy | ||
| moisture | resistance/capacitive probe, CM method, oven-dry weight | ||
| structure/moisture in depth | ultrasonic, seismic, radar, IR-thermography | ||
| masonry strength | unit cores + mortar joint strength; wallette (lab) | tap/scratch + rebound as preselection | |
| timber | resistograph (bore resistance), glue-area lab tests, moisture, fastener corrosion (destructive), pest expert | ||
| steel member | coupons for composition/strength, weldability check, coating thickness (ultrasonic), lead/asbestos in old coatings |
Site works order: photographic documentation → survey/control points → crack mapping incl. gauges on the building AND at neighbours → function checks of equipment → geometric control checks (dimensions, axes, storey heights vs. drawings) → actual use loads / occupancy audit → maintenance-state audit.
3.3 Pollutants (Schadstoffe) — periods to trigger testing
Seen-at-inventory list with manufacturing/use windows (FRG/GDR; if in doubt test):
- Asbestos: sprayed asbestos (soft insulation) GDR ≤1969 / FRG ≤1979;
weakly-bonded uses ≤1984; asbestos cement (Platten, pipes, flue linings) ≤1992; ban from 1995 (few exceptions).
- KMF (artificial mineral fibres): old wool installed until 31.5.2000;
recycled-bottle wool from 1996.
- PCB: facade/edge sealants old-Laender 1955–~1975 (peak 1964–72);
acoustic ceiling paints ≤1971; capacitors/transformers ≤1984.
- PAK (tar): waterproofing/bituminous single-plies ~≤1965; tar-asphalt screeds
≤ mid-1960s; parquet adhesives occasionally ≤ late 1970s; wood/timber protectants ≤ ~1991; wood-block mastic ≤1995; anti-corrosion coatings on water-works concrete ≤2000.
- PCP: indoor use effectively banned 1986 (FRG; outdoor until 1989), GDR
approvals ran to 1978/1986; total ban >0.1 M-% [VERIFY exact limit].
- Lead: water pipes ≤1973; lead-white/chromate paints until the 1980s;
PVC stabilisers only abandoned from 2015; red-lead primer never fully banned.
- Magnesia/anhydrite screeds: chloride content can attack RC slabs below —
check old "magnesiaestrich" floors before strengthening with bonded toppings.
Framework: Schadstoffkataster per VDI/GVSS 6202-1, level L1 (inventory + first assessment from drawings/period) → L2 (technical investigation: sampling programme, cadastre, risk assessment). Demolition/works spec follows the hazardous- waste demolition norm (ATV DIN 18459 logic) — asbestos/PCB handling is a separate trade with notification duties.
4. Material assessment of existing concrete structures
4.1 Two-stage strength derivation
- Stage 1 — documents/historic codes: read the concrete class from the old
calculation notes and map to a current characteristic cylinder strength (§ 4.3 tables). Rebar: ≥3 samples per table entry, ≥5 per test zone if the type is unknown or a higher fyk is wanted; one steel type per zone.
- Stage 2 — verification by sampling/lab if the documented class is doubtful,
missing, or a higher strength is needed for the re-check. GDR stock has its own rebar traditions (St A-0 220, St B-IV 490, Roxor oval bars 490 …) — see § 4.4.
4.2 In-situ strength testing (DIN EN 12504 + DIN EN 13791)
- Methods: cores (12504-1), Rebound (12504-2), pull-out (12504-3), UPV (12504-4);
classification of the result population per DIN EN 13791 (test zones of one "population"), with direct / indirect (Rebound calibrated) / combined calibration.
- Rebound discipline: ≥9 valid readings per area, spacing ≥25 mm, ≥25 mm from
edges; supplementary only — never the sole basis for a Nachweis [VERIFY scope].
- Cores: ≥3 per test zone; diameter ≥100 mm regardless of aggregate size;
length = diameter (dry-stored 50/100/150 mm cores equate to wet 150 mm cubes — DIN EN 13791 NA equivalence, the drying and shape-factor corrections cancel approximately); avoid longitudinal rebar (transverse bars reduce strength); test dry, defect-free. For new-build sampling the rule ≥1 per casting day per 100 m³ applies (≥3 per concrete composition); the relaxed 2-core rule is new-build only, never for Bestand. Relation f_ck,is,cube ≥ 0.85·f_ck,cube.
- Cube→cylinder, exact DBV/EN 13791 table (f_ck,is cylinder / cube, N/mm²): C8/10
7.0/9.0; C12/15 10.0/13.0; C16/20 14.0/17.0; C20/25 17.0/21.0; C25/30 21.0/26.0; C30/37 26.0/31.0; C35/45 30.0/38.0; C40/50 34.0/43.0; C45/55 38.0/47.0; C50/60 43.0/51.0 — use this table, not a flat 0.82 ratio.
- Rebound (Schmidt) without core calibration is only admissible per DIN EN
13791 if carbonation depth ≤ 5 mm (older stock: measure carbonation depth first; if > 5 mm the carbonated layer must be locally ground off before testing — rarely practicable, so calibrate instead).
Statistical reduction of a small test population (5 % fractile estimation), two approaches per DIN EN 13791 NA — pick by sample size and COV:
- Approach A (≥9 cores, or 3–8 cores with COV Vx > 0.20): lognormal/normal
5 %-fractile, fck,is = fm(n),is·(1 − kn·Vx), Vx = sx/fm(n),is with floor Vx,min = 0.08. kn by n (linear interpolation between): n=3→3.37; 4→2.63; 5→2.33; 6→2.18; 7→2.08; 8→2.00; 9→1.96; 10→1.92; 15→1.82; 20→1.76; 30→1.73; ∞→1.64.
- Approach B (3–8 cores, only if Vx ≤ 0.20): fck,is = min(fm(n),is·k3 ;
f_is,lowest + 4 N/mm²), with k3 by n: n=3→0.70; n=4–5→0.75; n=6–8→0.80. Simpler and less conservative than A but gated on the tighter COV — re-zone or add cores if Vx > 0.20 rather than force B.
4.3 Historic concrete classes → fck (cylinder, N/mm²) — mapping table excerpt
| Period / code basis | Old class | fck mapped | |
|---|---|---|---|
| 1904–1916 (W300 mean) | W180 / W200 | 8 / 9 | |
| 1916–1925 DAfEb W200 | 150 / 180 / 210 | 8 / 9.5 / 11 (extra conditions c) | |
| 1925–1932 DIN W200 | 100 / 130 / 180 | 5 / 7 / 10 | |
| 1932–1943 DIN W200 | 120 / 160 / 210 | 6.5 / 8.5 / 12 | |
| 1943–1972 DIN W200 (GDR TGL≤1980) | B120 / B160 / B225 / B300 | 6.5 / 11 / 15 / 20 | |
| " | Bc450 / Bc600 (precast, DIN 4225) | 30 / 40 | |
| 1972–1978 DIN W200 5 % | Bn50 / 100 / 150 / 250 / 350 / 450 / 550 | 4 / 8 / 12 / 20 / 27.5 / 35.5 / 43.5 | |
| 1978–2001 DIN W200 5 % | B5 / B10 / B15 / B25 / B35 / B45 / B55 | 4 / 8 / 12 / 20 / 27.5 / 35.5 / 43.5 | |
| 1980–1990 GDR TGL W150 5 % | Bk10 / 15 / 25 / 35 / 45 | 7.5 / 11.5 / 19 / 26.5 / 34 | |
| ab 2001 EN 206 (150 mm 5 %) | C12/15 … C40/50 | 12 … 40 |
Units: ≈ kp/cm² until 1972, N/mm² from 1978. Bn250 ≈ C20/25 is the standard bridge value used in re-check examples. fck,min structural concrete per class (with/without core support): C12/15→10/13; C16/20→14/17; C20/25→17/21; C25/30→21/26; C30/37→26/31 [VERIFY vs. current DIN EN 206 table].
4.4 Historic reinforcement fyk — mapping table excerpt (with ductility notes)
| Steel (period) | fyk N/mm² | class | |
|---|---|---|---|
| smooth St00.12 (1860–37) / hand iron St37 (1895–43) / rail-head <1930 | 180 / 220 / 130–210 | B | |
| high-quality rebar 1930–48 | 260 | — | |
| Betonstahl I (1943–72) | 220–245 | B | |
| Betonstahl II/III/IV (1948–72) | 315 | B | |
| St48 (1925–32) / St52 (1932–43), BSt IIa | 290 / 340 | B | |
| BSt220/340 GU · BSt420/500 RU(III) (1972–84) | 220 · 420 | B | |
| BSt420S (1984–2009); verwunden (twisted) | 420 | B / A | |
| BSt500S(IV); verwunden | 500 | B / A | |
| GDR St A-0 220 / A-I 240 / T-III 400 / T-IV 490 / B-IV 490 | as named | B mostly | |
| welded mesh GK(IV) (1972–84 onward) | 500 | A | |
| old high-strength specialty (bi-Stahl 70/90→650–700; Neptun 800) | — | B |
Notes baked into the tables: pre-1943 products carry a +10 % γM penalty; smooth bars do NOT satisfy current bond assumptions — anchorage/overlap must be checked against the DBV design-bond table for plain bars (fctd rises from 0.7 at fck=8 to 1.7 at fck=50 N/mm²; ×0.7 for "moderate" bond conditions, ×0.85 for non-quasi-static loading; favourable end hooks may be credited). Welded-mesh codes (Q/R/N/A/B ranges) identify the era; strength of the plastic-knot composite mats era is special.
4.5 Old-code detailing artefacts to hunt for (they change the Nachweis)
- Steel strain capped at 5‰ in the old σ/traglast world → under EC2 the
member may be "over-reinforced in strain" though under-reinforced in force: crack-width and ductility verification become the binding check (§ 6.1).
- No stirrups (rammed/poured old slabs, τ0 tables allowed it) → beware
splitting cracks along span direction; shear then rides on V Rd,c only.
- Little or no top (field) rebar over supports; cranked bars (Aufbiegungen)
with outdated shear-cover logic; corbel/curtain-wall anchors; old rivet edge distances where steel parts are reused.
- Old cover ≈25 mm vs. today's 30–40 mm → in 50-a stock the carbonation front
(§ 8.1) often already reaches the bar level.
4.6 Modified partial factors for the re-check (qualified inventory only)
Preconditions (all, DBV-Merkblatt "Modifizierte Teilsicherheitsbeiwerte", 03/2013): design working life 50 a; ≥5 a of proper existing use proven; qualified survey proves damage-free condition; predominantly static live loads Qk ≤ 5 kN/m² and point loads (Gk+Qk) ≤ 7 kN; load ratio 1.0 ≥ Gk/(Gk+Qk) ≥ 0.50; normal concrete C12/15–C50/60; section tolerances per DIN EN 13670/DIN 1045-3:2012 met (else measure and use as-built geometry). Then — and only with prior agreement of the Prüfingenieur/authority —:
- resistance factors γ_M per COV of the measured material (DBV modified-factor
table):
| COV of concrete | γ_M concrete (persistent/transient) | γ_M steel | |
|---|---|---|---|
| 0.25 | 1.20 | 1.05 | |
| 0.30 | 1.25 | 1.10 | |
| 0.35 | 1.30 (design stage only w/o member test variant) | 1.10 | |
| 0.40 | 1.40–1.50 (bending RC members +20 %; axial/shear of unreinforced bending +40 % centric-compression caveats) | 1.10 |
Extraordinary-situation variant: γ_M concrete 1.10–1.30, steel 1.00. Justification: shorter residual life + small geometric scatter of ONE known member beat the population-wide calibration of new-design factors. Floors on the COV itself, regardless of test result: V_y,c ≥ 0.15, V_y,s ≥ 0.06; without member testing (design/Entwurf stage only) default to V_R,c = 0.30 → γ_C,mod = 1.30 and V_R,s = 0.10 → γ_S,mod = 1.10. Design values: f_cd,mod = α_cc·f_ck,is/γ_C,mod with α_cc = 0.85 for reinforced concrete, 0.70 for plain/unreinforced concrete; f_yd,mod = f_yk,is/γ_S,mod.
- A separate, simpler route (DAfStb Belastungsrichtlinie, for the preparatory
capacity assessment, same preconditions) fixes single values instead of the COV table: γ_G reduced 1.35 → 1.15 (permanent actions), γ_Q unchanged at 1.50 (variable actions), γ_C reduced 1.50 → 1.40, γ_S reduced 1.15 → 1.10. Never mix this set with the DBV COV-table set in one verification, and never adjust γ_G alone without also reviewing the resistance side — an isolated single-factor cut can silently lower the overall safety level below intent.
4.7 Load tests as last resort
DAfStb load-test guideline: computed capacity first, load-controlled testing, only accredited test institutes (MPA/university) — risk of sudden shear-compression failure under the jack. Use where strengthening is otherwise disproportionate.
5. Actions for existing buildings (load assumptions)
- Unit archaeology: 1 Mp/m² = 10 kN/m²; 1 kp/cm² = 0.1 N/mm²; old W-classes
are cube crush strengths, not fck — convert before touching EC2 tables.
- Historic use loads: the DIN 1045:1972 dwelling-slab check ran on q = 7.0
kN/m² total (§ 6.1); modern categories: A2 residential 1.5 (+1.0 partitions), B1 office 2.0 kN/m² — living→office raises q modestly, storage explodes it; classify the target use first.
- GDR-era action factors (ETV Beton 1981, semi-probabilistic): γ self-weight
normal concrete 1.10, insulation 1.30, snow 1.40, wind 1.20 — a GDR "Traglast" safety margin is NOT an EC2 utilization; re-derive, don't translate coefficients.
- Snow: today's snow zones/heights differ from the maps at erection (and the
modified-γ table explicitly addresses the German lowland snow case as an "extraordinary" situation) → for roofs, the Nachrechnung snow action follows the CURRENT DIN EN 1991-1-3/NA [VERIFY the Bestand-specific snow relaxation debate — some authorities allow the erection-date map for unchanged fabric under Bestandsschutz; do not count on it].
- Added loads typical to Bestand: PV/ballast on flat roofs, green roofs,
mezzanines, racks/forklifts, safes/cranes, summer→ice-rink hall conversions (temperature/humidity regime change!) — each is a VDI 6200 "damage indicator class 1" trigger for re-check.
- Imposed-deformation actions (shrinkage/creep residual, temperature in old
monolithic frames) rarely documented; measure crack widths before assuming they are dormant.
6. Verification worked examples (the numbers to imitate)
6.1 1975 RC slab, living → office, three-stage re-check
Geometry/stock: one-way slab, effective span 4.34 m (+support width → l_eff≈4.50 m), h = 180 mm, d = 155 mm, concrete Bn250 (≈C20/25), steel "III 42/50" (BSt420), provided As = 5.24 cm²/m (Ø10/15).
Stage 0 — historic proof (DIN 1045:1972): q = 7.0 kN/m²; m_F = 1.772 Mp·m/m → a_s,erf = 5.15 ≤ 5.24 OK; shear at 0.5d τ₀ = 1.11 < 3.50 → no stirrups; l/h = 29 ≤ 35 for deflection. The slab was fine under its own code.
Stage 1 — EC2 with new use, NO survey: fyk downgraded by the old→new total- safety ratio (1.40·1.15)/1.75·420 = 384 MPa → fyd = 334; fck = 20 → fcd = 11.33; loads g = 6.0 (1.5 new floor + 4.5 old allowance), q = 2.0 (office B1): r_d = 1.35·6 + 1.5·2 = 11.1 kN/m² → m_Ed = 28.35 kNm/m → μ = 0.1041 → ω = 0.1103 → a_s,erf = 5.80 > 5.24 cm²/m → fails (−11 %). Shear: v_Ed = 22.37 kN/m vs. v_Rd,c ≈ 58.6 kN/m (k=2.0, ρ_l=0.34 %) OK. Deflections: historical record < l/250 → waivable.
Stage 2 — modified γ after qualified survey: 9 cores Ø100 (h/d≈1) → lognormal statistics (EN 1990 Annex D): f_cyl = 0.82·f_cube; mean 3.41 (ln), s = 0.174 → fck,is = e^(3.46−1.96·0.174) = 22.70 N/mm²; V_D = √(0.05²+0.05²+0.176²) = 0.189 → DBV table gives γ_c,mod = 1.20, γ_s,mod = 1.10 → fcd = 16.08, fyd = 382; measured d = 151 mm (as-built) → μ = 0.077 → a_s,erf = 5.11 ≤ 5.24 → OK. Strain check: εs = 25‰ exceeds the old 5‰ design cap → SLS governs: quasi-permanent r = 6.6 kN/m² → m = 16.86 kNm/m → σs ≈ 237 N/mm²; XC1 w_k = 0.4 mm → limiting bar Ø* = 24 mm, Øs = 24·fct,eff/fct,0 = 18 > 10 provided → cracking OK.
Moral: survey + modified factors turned an −11 % flexural failure into a pass without strengthening; the old code's missing ductility is re-covered by the crack-width proof, not by more steel.
6.2 Slender existing column — 2nd-order re-check (1985 stock)
30/30 cm, As = 8.04 cm² (4Ø20, fyk 450→fyd 435), l = 5.2 m, l₀ = 0.76·l = 3.95 m. Cores n=6: mean 43.41 cube, s = 5.07, V = 0.117 → EN 13791 approach B: fck,is = min(0.8·43.41 = 34.73; 37.52+4) = 34.73 cube → fck = 33.5 cylinder → C30/37. Slenderness: λ = 45.6 > max(25; 16/√ν_Ed) → slender, 2nd order. Accidental ecc e_i = αh·l₀²/2000-type ≈ 0.87 cm (αh from length; use code formula); creep second-order e₂ = K_r·(fcd·…)·h ≈ 0.46 cm (K_r verified afterwards via (N_Ed−N_Rd)/(N_Ed−N_bal) = (2.058−1.844)/(2.058−0.683) = 0.156 ≈ assumed 0.16 ✓). e_tot = 1.33 cm → ω = 0.205 → column interaction chart (BT 2c, d₁/h 0.15, e_d/h 0.044 line) → N_Rd = 1844 kN ≥ N_Ed → utilization ν_Ed = 1.08 [the example's own load level; treat >1.0 as the strengthening trigger]. Procedure to copy: strength from cores → class → slenderness gate → eccentricities → chart/numerical interaction → K_r self-consistency check.
6.3 Re-check report skeleton (what a Tragwerksplaner expects)
- object + construction type + GK/CC classification (VDI 6200); documents found
vs. assumed (mark every assumption),
- survey programme + results (zones, statistics, fck,is, fyk proven); code path
declared (§ 2.1–2.3, no mixing),
- member utilization table (ULS + SLS, as-built geometry) + detailing audit vs.
old-code artefacts (§ 4.5),
- deficits + option list (§ 7) incl. staging checks for execution states,
- monitoring plan (§ 1 phase 5) and Bauwerksbuch entry.
7. Strengthening methods (Ertüchtigung) — options with numbers
Method families: added section (cast-in-place Aufbeton/jacket or Spritzbeton shotcrete, with or without reinforcement, bonded or slot-bonded), prestressing, change of structural system, injection; materials: concrete/shotcrete + rebar, steel lamellae/sections, CFRP/GFRP/AFRP laminates & sheets. Composite action behaves like a built-up section: bond laws govern, the joint/interface ends are the critical zone (delamination), and unloading the existing member boosts the efficiency of every method (remove partitions/passive load, or jack actively).
7.1 Concrete topping (Aufbeton) + added reinforcement — flexure of slabs
Rules:
- thickness ≥ 40 mm (shotcrete toppings thinner only by approval [VERIFY]);
interfacial reinforcement anchored on BOTH sides of the joint;
- bending checks on the MONOLITHIC section use the LOWER of the two concrete
strengths for the compression-zone contributions [VERIFY exact DAfStb rule];
- all intermediate construction stages checked (wet concrete weight before bond
exists!);
- surface prep: shot-blasted + bonding bridge; joint shear verified below;
- added bars: small-dense (e.g. Ø6/20 B500B = 1.41 cm²/m) placed near the bottom
of the topping.
Joint shear. DIN EN 1992-1-1's interface-shear model is validated for new-build only ("abgesicherter Bereich"); for strengthening of existing members use the fib Model Code 2010 approach instead (Wendehorst/DAfStb practice). Unreinforced interface (rigid bond):
τ_Rdi = [c_a·f_ctd + μ·σ_n] ≤ 0.5·ν·f_cd
Reinforced interface (perpendicular bond reinforcement, ρ = A_s/A_i):
τ_Rdi = c_r·f_ck^(1/3) + μ·(σ_n + ρ·κ1·f_yd) + ρ·κ2·(f_yd·f_cd)^0.5 ≤ β_c·ν·f_cd
with ν = 0.55·(30/f_ck)^(1/3) ≤ 0.55 (compression-strut strength reduction), and roughness classes (R_t = Kaufmann sand-patch depth):
| Joint surface | R_t | c_a (adhesion) | c_r (interlock) | κ1 | κ2 | β_c | μ (f_ck≥20) | μ (f_ck≥30) | |
|---|---|---|---|---|---|---|---|---|---|
| sehr rau (very rough) | ≥3.0 mm | 0.50 | 0.2 | 0.5 | 0.9 | 0.5 | 0.8 | 1.0 | |
| rau (rough) | ≥1.5 mm | 0.40 | 0.1 | 0.5 | 0.9 | 0.5 | 0.7 | 0.7 | |
| glatt (smooth) | — | 0.20 | 0.0 | 0.5 | 1.1 | 0.4 | 0.6 | 0.6 | |
| sehr glatt (very smooth) | — | 0.025 | 0.0 | 0.0 | 1.5 | 0.3 | 0.5 | 0.5 |
μ jumps with concrete class (rougher/higher-strength joints get more friction credit at f_ck≥30) — don't reuse the f_ck≥20 column once the topping is C30/37+. Surface prep and cleanliness governs which row applies; sand-patch method is imprecise (an optical roughness method is recommended in practice) — when in doubt, classify one row down.
Worked topping example (2-span 6.25 m, existing h=18 cm, Ø12/11 = 10.28 cm²/m, new 5 cm topping): loads g_k = 7.25, q_k = 1.5 (A2) → r_d = 12.05 kN/m²; support moment M_B = −0.125·12.05·6.25² = −58.8 kNm/m → existing section alone needs 11.51 > 10.28 → add 1.41 cm²/m in the topping → resultant d = 15.1 cm → μ = 0.205 → required total 10.91 ≤ 11.69 cm²/m OK. Shear: A-field d = 19.5, ρ_l ≈ 0.13 % → v_Rd,c = 54.2 > v_Ed 25.2; B-support on OLD depth d = 14.5, ρ_l = 0.71 % → v_Rd,c = 70.2 > 43.9 → no shear links. Joint check (smooth class, c_a = 0.20, μ = 0.6): τ_rd = 0.2·f_ctd ≈ 0.17 ≥ ν_Ed = 0.165 at the high-shear support → plain joint just OK (bare margin — a shot-blasted "rau" joint buys the safety). Rule of thumb: verify the joint where the moment is NOT maximum.
7.2 Column jackets — cast-in-place or shotcrete (Spritzbeton)
Function: adds area and confinement; shotcrete jackets per tunnel-lining rules (DIN 18551 §9.5 / DIN EN 14487 product logic):
- no lasting force transfer at jacket ends — load introduction is by bearing
plates/wedges or a designed taper; added longitudinal bars only counted where force closure exists (head & base details);
- checks: base/head load-transfer zone, mid-height composite section, confinement
contribution;
- detailing (DIN 18551 §9.5 / DAfStb Heft 467): closed hoops per EC2NA fig.
NA.8.5g/h or welded links, longitudinal bars concentrated at hoop corners; intermediate anchors (Zwischenverankerungen) required once h/b > 1.5; load-introduction zone hoop spacing ≤ 80 mm, zone length l_c = 30·d_s (DIN 18551) or 2·d_k (DAfStb Heft 467, use the larger); shotcrete shell contributes to mid-height capacity only, at a 0.80 efficiency factor (shrinkage/bond loss) — never assumed to transfer force at the jacket ends (no lasting force closure there without bearing plates/wedges).
Confinement gain (effective confined area + capacity add):
A_c,eff = λ_q·λ_l·A_k, A_k = b_k·d_k
λ_q = 1 − [2(b_k−d_s)² + 2(d_k−d_s)²] / (5.5·A_k) — corner-loss factor (d_s = corner longitudinal-bar diameter)
λ_l = (1 − s_bü/2b_k)·(1 − s_bü/2d_k) — hoop-spacing loss factor (s_bü = hoop pitch)
ΔN_Rd = 2.3·k_β·ρ_q·f_yd,bü·A_c,eff, with k_β = 1 + (f_ck−20)/100 ≥ 1 and ρ_q = A_q/A_k = 2(b_k+d_k)·(A_bü/s_bü)/(b_k·d_k)
Old and new hoop confinement areas are computed separately (A_eff,alt + A_eff,neu) and their ΔN_Rd contributions summed. Head/base capacity (bearing transfer only, no shell credit): N_Rd = A_c,alt·f_cd,alt + A_s,alt·f_yd,alt + ΔN_Rd,1 + ΔN_Rd,2
Mid-height capacity (shell credited at 0.80): N_Rd = A_c,alt·f_cd,alt + A_s,alt·f_yd,alt + 0.80·A_b,neu·f_cd,neu + A_s,neu·f_yd,neu
Eccentricity reduces the confinement add (DIN 1045:1972-derived, retained in practice): ΔN'_Rd = ΔN_Rd·(1 − 8M/(N·d_k)).
Worked jacket example (30/30 B35→assessed C30/37, IV steel fyk 500, l₀ = 2.8 m, N_Ed 1800 → 2300 kN): existing column N_Rd ≈ 1871 kN (ecc. ω = 0.383 chart) → deficit ~430 kN. Jacket 7.5 cm C30/37 + 4Ø16: mid-height added capacity with 0.8 shotcrete factor ≈ 1880 kN (plain area+steel). Confinement: existing hoops (s = 20 cm) add only 54 kN (λ_q 0.389, A_eff 0.00762 m²), jacket hoops (s = 7.5 cm) add 478 kN (λ_q 0.331, A_eff 0.0412 m², ρ_w = 0.0107); eccentricity-reduction term (DIN 1045-1972 confined-member rule, retained in practice) 0.86. Load-introduction zone governs: N_Rd,tot = 1871 + 0.86·(54+478) = 2328 > 2300 OK (util 0.99); mid-height = 1871 + 0.86·1880 = 3488 OK. Detailing: cover XC1 c_min 10 + Δ_dev 10 → c_nom 20 ≤ 25 provided; jacket stirrups Ø≥6, spacing ≤ min(12Ø_s, h, 30) = 19.2 → 17.5 mid; transfer zone l_c = max(30Ø_s = 48; 2·d_j = 78? shown 12@75=90≥78) → 12 stirrups @75. Lesson: the head/base transfer capacity, not the middle, sets the jacket length and congestion — detail it first.
7.3 FRP strengthening (CFRP laminates/sheets)
- Products: pultruded laminates (CarboDur S/M class; 160/2400-type naming) bonded
with epoxy (MC-DUR 1280, Sikadur-type, StoPox SK41) or slot-in (Schlitzverfahren); system approvals (Z-36.12-xx) carry expiry dates — always use the current abP/ETA, never a lapsed one.
- γ_M (DAfStb-Richtlinie bonded-reinforcement guideline, persistent/transient →
extraordinary): CFRP laminate γ_LL 1.20 → 1.05, CFRP sheets/gelege γ_LG 1.35 → 1.10; bond adhesive γ_BA 1.50 (bonded) → 1.20, γ_BE 1.30 (slotted) → 1.05; steel-on-steel or CFRP-on-CFRP bond γ_BG 1.30 → 1.05.
- Laminate material properties for FEM/BIM (elastic, ≥-values per abZ, N/mm²
unless noted): CarboDur S — ultimate strain ε_Luk ≥1.6 %, E_Lk ≥161,900, E_Lm ≥170,000, f_Lk ≥2800; CarboDur M — ε_Luk ≥1.3 %, E_Lk ≥200,000, E_Lm ≥210,000, f_Lk ≥2500; MC-DUR/Carboplus 160/2400 — ε_Luk ≥1.6 %, E_Lk ≥160,000, E_Lm ≥162,000, f_Lk ≥2800; MC-DUR/Carboplus 160/2800 — ε_Luk ≥1.8 %, E_Lk ≥164,000, E_Lm ≥168,000, f_Lk ≥3200; MC-DUR/Carboplus 200/3000 — ε_Luk ≥1.5 %, E_Lk ≥190,000, E_Lm ≥200,000, f_Lk ≥3200; S&P 150/2000 — ε_Luk ≥1.5 %, E_Lk ≥160,000, E_Lm ≥168,000, f_Lk ≥2350; S&P 200/2000 — ε_Luk ≥1.3 %, E_Lk ≥200,000, E_Lm ≥210,000, f_Lk ≥2500. E_Lk is the characteristic (design-side) modulus, E_Lm the mean — use E_Lm for FEM stiffness/deflection, E_Lk for ULS strength checks. Laminate thickness typically 1.0–3.0 mm, width 10–150 mm (slot-bonded strips narrower, 10–30 mm) — geometry per the current abZ/ETA, not the type table alone. All approvals (Z-36.12-xx) carry an expiry date — confirm current before use, never model a lapsed system.
- Section analysis: plane sections, no concrete tension, perfect bond up to
debonding; checks per member: peeling (interfacial crack) / anchorage bond line AND tensile rupture line, plus V Rd,c,max and durability of the adhesive (temperature!); redistribution allowed only in un-strengthened zones.
- Fire/impact/creep of adhesives are the weak link vs. steel plates; slotted CFRP
survives edge delamination better.
- Steel lamellae follow the same composite logic with steel γ_M0-type factors;
unbonded post-tensioned strips are a prestress variant (§ 7.5).
- Carbon-textile-reinforced overlay (Carbonbeton) alternative: a thin fine-
grain-concrete layer (≈2 mm max aggregate) with an embedded carbon grid, laminated or sprayed onto the tension face — less invasive than jacketing and adds no corrosion risk to the existing member (non-metallic reinforcement). German route: DAfStb-Richtlinie "Betonbauteile mit nichtmetallischer Bewehrung" (in force since early 2024) combined with the relevant DIN 1045 parts; individual products still need their own abZ/aBG (documented example: Z-31.10-182). Detail parameters in concrete-detailing §18. VERIFY current guideline edition and product approval before specifying.
7.4 Steel sections / plates to existing members
Bolted/welded steel additions to concrete ride on post-installed anchors with cracked-concrete approval (rebar scan FIRST to avoid hitting old bars) or epoxy grout beds in bearing. Typical: side/bottom plates on beams, lacing on columns, inserted bracing (system change § 7.6). Design per current steel code as new; the interface is a new connection either way (anchor tables: concrete-detailing skill).
7.5 Prestressing (Externale Vorspannung)
External tendons (threadbars over deflection blocks) or jacked strips: the ACTIVE method — it reduces existing stresses and crack widths instead of only adding capacity, and controls deflection. Losses, deviation-block bearing and anchorage bursting are checked on the OLD concrete strength; fire protection and anchor inspection per approval [VERIFY current guideline numbers — method level here].
7.6 Adding walls / changing the structural system (Nachträgliche Aussteifung)
For unbraced or RC1-type frames (single-storey column-stabilised halls, propped cantilevers without continuity): introduce shear discs or a core.
- Masonry infill/added RC or timber-sheathed walls act as discs — keep the "longest
bracing walls perpendicular to the largest facade" rule; ≥3 non-parallel non- concurrent rigid points per diaphragm;
- floors as diaphragms need edge chords + collectors: old screed joints and
openings (stair voids!) break the chord — steel strap chords are the standard Bestand fix;
- Ringanker/Ringbalken (hoop beam/cordon) added at roof & floor level turn
non-ductile masonry stock into a box (classic seismic retrofit, see the seismic skill for ductility detailing);
- moment-frame trade: adding fixity creates base moments ∝ storey height and
drift ∝ H³ — fixed old columns only work up to ~2–3 storeys [rule of thumb];
- CLT/steel bracing inserted inside avoids facade change (heritage logic).
7.7 Foundation underpinning (Unterfangung, DIN 4123)
- Unterfangung = transferring existing footings to a deeper/broadened bearing
level; Ausschachtung = excavation whose soil wedge initially still aids stability.
- Sectional pits: max ~2 m wide [OCR-lost exact figure], work high-load zones
(cross-wall intersections, corners) FIRST, force-fit (Kraftschluss) the new footing via steel double wedges or hydraulic jacking, build the new footing immediately — the old footing must never hang unsupported across a pit.
- Execution sequence discipline replaces interim stability proofs: with the rules
kept, no per-stage stability check is demanded; the FINAL state gets the full EN 1997-1 set (overturning, sliding, bearing, slope, deep slip, material).
- Settlement during underpinning: hairline cracks and displacements ≤ 5 mm are
deemed largely unavoidable — set the Beweissicherung trigger levels around that.
- Adjacent-structure protection follows excavation logic (prestressed struts,
diaphragm/pile walls for sensitive neighbours) — geotechnics skill.
7.9 Cathodic protection (Kathodischer Korrosionsschutz, KKS)
For chloride-driven corrosion (§8.2) that patch repair cannot outrun — chlorides already diffused past the bar depth, so cutting out contaminated cover just exposes fresh chloride-laden concrete next to it — KKS stops the electrochemical process itself instead of removing/replacing contaminated concrete: a protective current (surface-applied or embedded anode mesh, impressed-current or sacrificial) polarises the reinforcement cathodically, halting further metal loss without removing sound concrete. [Digested from Wietek, Beton – Stahlbeton – Faserbeton, 2024 — case-study level, not a design code; the technique itself is standardised in DIN EN ISO 12696, VERIFY current design values there.]
- Monitoring: embed a reference electrode (CMS-type, silver/silver-chloride)
in the at-risk zone before or during the KKS retrofit; it reads pore-water content, chloride content and active corrosion rate at the bar. Install it before corrosion is visible — KKS is most effective started early — and use ongoing potential mapping to trigger the decision rather than waiting for visible rust staining, which already means active section loss.
- Approximate unmaintained service life by exposure (years, order-of-magnitude,
single-source digest — VERIFY against project-specific durability design / DIN EN 1990 design-life classes before use in a report):
| Exposure | Plain concrete | Ordinary RC | Fibre-reinforced concrete | |
|---|---|---|---|---|
| Dry air | 300 | 150 | 200 | |
| Humid air | 300 | 120 | 200 | |
| Damp soil | 250 | 40 | 200 | |
| Acid rain | 250 | 40 | 200 | |
| De-icing salt spray | 200 | 30 | 200 | |
| Salt mist | 200 | 40 | 200 |
With one traditional repair cycle, RC life extends by roughly +50 a (dry/humid air), +30 a (damp soil/acid rain) or +25 a (salt exposure) — always shorter than a comparable new build, because residual cracks and material mismatch remain. With KKS instead of traditional repair, the digest reports a flat +100 a across every moisture/chloride exposure class — the gap is largest, and KKS is most worth considering, exactly where salt exposure is present.
- Whole-life economics (documented case, Wietek 2024): conventional periodic
Sanierung of a chloride-exposed RC bridge typically needs full replacement after ≈35–40 a once bar corrosion undermines capacity (a "Sanierung → Abriss/Neubau" cycle repeats); continuously-monitored + polarised KKS avoided that endpoint at roughly 1.8× lower whole-life cost than the repeat-repair-then-rebuild cycle in that case — the saving comes from never reaching demolition. Treat the factor as an order-of-magnitude planning input, not a quotable ratio for a new case.
- Track record: proven >100 years on buried steel pipelines; used on German-
speaking-area road bridges since the 1990s (documented case: 9 Brenner-Autobahn bridges fitted with KKS as an early large-scale DACH application). KKS only works if kept running and monitored — a documented case of KKS systems being switched off without recorded technical justification put the affected bridges back at corrosion risk with no active protection. If you inherit or recommend a KKS system in a Bestandsaufnahme, verify it is live, monitored and its records are current — a de-commissioned-but-unflagged KKS system is worse than assuming none was ever installed, because it hides an unprotected chloride exposure behind an apparently-solved problem.
- When to reach for it vs. §7.1–7.2: KKS is the arrest-in-place option when
concrete removal would be extensive/structurally risky or chlorides are already deep (pitting risk, §8.2); Aufbeton/jacketing (§7.1–7.2) stay the default when the deficiency is capacity, not active ongoing corrosion — the two are not mutually exclusive (KKS can protect a jacketed member going forward).
7.8 Method-selection cheat sheet
| Deficit | First-choice options | Watch | |
|---|---|---|---|
| slab bending −5…−15 % | Aufbeton + bars (§ 7.1) | joint shear, stage loads, build-up height/doors | |
| slab bending, height-constrained | CFRP soffit (§ 7.3) | peeling, fire, edge distance of slots | |
| column N-deficit small | CFRP wrap (confinement only) or jacket | end transfer (§ 7.2) | |
| column N-deficit large | shotcrete jacket w/ own hoops | head/base detail, 0.99 margin ≠ reserve | |
| beam shear deficit | CFRP U-jackets/side bonded; steel flange straps | anchorage against peel | |
| hall unbraced | added bracing/wall (§ 7.6) | diaphragm chords, transfer at foundations; bearing deficit → widen/underpin (§ 7.7) with 5 mm settlement honesty | |
| deflection/serviceability | prestress strips (§ 7.5) | old-concrete bearing at deviators | |
| active chloride corrosion, chlorides already past bar depth | Cathodic protection / KKS (§ 7.9) | needs continuous power + monitoring; verify any inherited system is still live before relying on it |
8. Defect catalog — mechanism, signature, first action
8.1 Carbonation-induced corrosion (the default 50-a RC disease)
- Mechanism: CO₂ + moisture carbonates cement stone → pH < 9 → passive film dies →
uniform (Flächenkorrosion) rust; rust volume ≫ steel → splitting pressure → cracks parallel to bars → cover loss → "puff-pastry" section loss. Needs RH ≈ 45–95 % window; dry or saturated concrete barely carbonates; freely weathered = fastest.
- Progression: d_k = α·√t; example 5 mm at 10 a → α = 1.58 mm/√a → ≈ 11.2 mm
at 50 a; compare with as-built cover (old 25 mm!) — d_k ≥ c means plan corrosion.
- Signatures: rust staining at bars (Rostfahnen), map/hairline cracks along rebar,
hollow sound on tap, spalls at edges/splines; phenolphthalein stays colourless.
- Actions: remeasure depth, half-cell for activity, corrosion-inhibiting repair
(realk Aktivierung) or cover restoration; structural check of residual section.
8.2 Chloride attack (XD/S classes, de-iced decks, coastal)
- Pitting (Lochfraß): localised deep attack, **little surface warning, sudden bar
failure** — worse than carbonation for residual capacity. Chlorides ride water- filled pores; Volhard/titration profile vs. depth; old concrete often lacks the w/z ≤ 0.45–0.55 density of modern XD3 concrete.
- Actions: profile sampling, potential mapping, remove chloride-loaded cover +
re-alkalise, or isolate surface (drainage!); structural: assume pitting loss ratios [VERIFY DBV Heft Instandsetzung assumption set].
8.3 Frost + de-icing salt (XF)
- Scaling needs saturation + fine pores; air voids (1–5.5 Vol.-% by Dmax class)
are the defence old lean mixes lack; damage concentrates at splash zones, deck edges, parapet feet. Drainage first, then SR/PO repair mortar.
8.4 Cracks: classification that decides the repair
| Type | Typical cause | Pattern | Repair logic | |
|---|---|---|---|---|
| unschädlich/statisch ruhig (dormant) | shrinkage ~0.6 mm/m final, temperature early | fine, even spacing, mid-depth of restrained zones, stable vs. gauge | seal for durability only | |
| aktiv (moving) | live restraint, cyclic thermal, ongoing settlement | width changes with season/load, gauge drift | move the joint (open it properly) or relieve the restraint, then seal | |
| load-carrying (statisch wirksam) | shear/flexure/punching overload | diagonal in shear span; vertical flexure at max M (soffit); punching cones/punctuations at column heads of flat slabs | STRUCTURAL re-check before sealing | |
| splitting along bars | corrosion, old no-stirrup rammed concrete (Stopfbeton) | longitudinal cracks over bars, rust in the crack line | § 8.1 + shear re-check | |
| settlement | differential bearing, adjacent excavation | diagonal cracks at stressed corners of openings, vertical at soft-storey/abrupt stiffness change, bulged masonry wythes | underpin or relieve; ≤5 mm honesty (§ 7.7) |
Crack-width gauges (Rissmonitore) over one full seasonal cycle distinguish aktiv vs. ruhig empirically; self-healing (Rehydratation crystallisation) can close hairline cracks < ~0.1–0.2 mm in wet phases [VERIFY size bound].
8.5 Alkali-silica reaction & chemical attack (XA)
ASR (AKR): reactive silica (flint, opal sandstone, greywacke) + alkalis + moisture → swelling gel → map cracking, gel exudation, deck-edge spalls; diagnose via core microscopy + aggregate alkali class; measure = cut the moisture; diffuse stiffness loss → re-check with reduced modulus [VERIFY factor]. Sulphate: expansive route (sulphate → ettringite — old high-C3A CEM I in sewage/slurry exposure is a known failure class) vs. dissolving route (acids/fats leach paste → soft chalky surface, white blooms); check surface pH and reduced section.
8.6 Timber defects (assessment-level)
Rot fungi need MC > ~18–20 % (true house dry rot Serpula active from 20 % with a moisture reservoir; brown/white rot, blue stain cosmetic); insects (Nagekäfer common furniture beetle, Hausbock, Splintholzkäfer) attack even dry wood; shrinkage/warp loosens old joints; beam heads (Balkenköpfe) in damp masonry are the classic rot pocket; load-duration: old timber strength assumes short-term — 50-a sustained strength ≈ 60 % of short-term. Resistograph for hidden decay; DIN 68800 hazard classes GK0–GK4 [timber-specifics in the timber skill].
8.7 Steel defects (assessment-level)
Coating damage → section loss (ultrasonic thickness at worst spots); fatigue under cyclic crane/traffic loads: look at weld ends, old rivet groups, missing or loose bolts (locking must be chemical/mechanical, not friction only), flange wear debris = overload evidence; deformation/out-of-plumb = impact history. Lead and asbestos paints: sample before blasting (§ 3.3).
8.8 Envelope deterioration signatures (from the damage-indicator checklist)
- Pitched roofs: slipped tiles (wind), leaky chimney/window junctions, gutters
frozen/ponding; flat roofs: ponding, wet/blistered insulation, added ballast (PV/greening) overload, missing/undersized emergency overflow, deflection ponding feedback loop;
- facades: spalled corners of two-leaf outer wythe (corner restraint against wire
anchors), bulging, open/eroded joints (driven-rain class III exposure), efflorescence, stalactites inside = persistent water path (white-tub failure);
- floors: leaking pipe pockets, wet screed, magnesia screed + chloride combo (§ 3.3);
- decks/parking: rutting, failed joints, signage-load confusion; bearings seized;
expansion joints bridged (spalled lips) = active restraint present (§ 8.4).
9. Moisture and mould remediation (Feuchtesanierung)
Goal restated: not dryness, but no persistent moisture — allow occasional wet plus guaranteed drying. Diagnostic ladder: locate source first (rain vs. ground vs. condensation vs. leak vs. construction moisture Baufeuchte), then choose the measure; moisture maps (capacitive grid + CM/oven-dry profiles) before any remedial contract.
Measure ladder (escalate only as far as proven necessary):
- user-side: ventilation concept (see § 10.5), dehumidify, remove vapour
sources; fRsi ≥ 0.7 mould criterion at θ_i 20 °C/θ_e −5 °C/φ_crit 80 % [and fRsi,min up to ~0.94 for pool-type climates — per DIN 4108-3 logic];
- surface: rain-tightness repair (joints, render, drip edges), clear
ponding/gutters, raise ground levels away from plinth, repair drainage;
- plinth/ground: continue the waterproof/insulation package 30–50 cm above
finished ground; Querschnittsabdichtung (cross-section seal) in masonry bed joint cuts off capillary rise — injection barrier = specialist discipline [VERIFY product Z-requirements]; dense hydrophobic plinth render transition;
- basement classes: Bodenfeuchte (simple coat) → stauendes Sickerwasser
(full tanking) → drückendes Wasser (protected tanking; black-tub sheet wrap or WU white-tub concrete logic: crack control + waterstops at construction joints; never coat on top of soft insulation under point load);
- drainage package: filter fleece → drainage mat → pipe at footing to
soakaway/separator (control shafts, fall rules per drainage design);
- drying after damage: dehumidification only where an outward-drying path
exists; wet insulation (λ water 0.6 vs. air 0.025 ≈ 24×) is REPLACED, not dried in place.
Mould: surface treatment + remove the humidity cause; indoor-air measurement campaigns per pollutant protocols; HVAC condensation (summer ice-rink-type regimes § 5) needs ventilation, not chemistry.
10. Energy retrofit of the envelope (energetische Ertüchtigung)
Demand context: unsanitised old stock runs 200–270 kWh/(m²a) heat demand (1980 levels), average today ≈ 130, target 15–50 for new-standard fabric; a staged retrofit can cut demand by up to ~85 %. Law stack: WSchV/HeizAnlV → EnEV → GEG 2020 (amended 2024) → the services framework already names a GModG from 2026 — check the in-force text at project date [VERIFY].
10.1 Owner obligations
GEG-style component limits (Bauteilegrenzwerte) bite on owners when elements are replaced or first insulated (and historically on large buildings after central-plant replacement): the retrofit U-maxima below are the numbers to design to. Plus: 65 % renewable share for new heating installations (municipal heat planning WPG 2024 rolling out; a 2026 relaxation debate is flagged — [VERIFY at project date]); airtightness certificate when no blower-door history; old low-efficiency boilers/insulation retirement duties exist in the EnEV/GEG lineage [VERIFY current transition clauses]. Non-compliance is a fine risk AND a subsidy blocker (BEG requires deeper-than-code fabric).
10.2 U-limit table for existing elements (19 °C rooms / 12–<19 °C halls)
| Element | U max W/(m²K) | |
|---|---|---|
| external wall (replace or first insulation) | 0.24 / 0.35 | |
| cladding/re-render with insulation | 0.24 / 0.35 (exempt if built to rules after 31.12.1983) | |
| windows to outside | 1.3 | |
| roof/top-floor ceiling | 0.24 | |
| roof (membrane-covered flat) | 0.20 | |
| roof windows | 1.4 | |
| glazing-only replacement | 1.1 (box windows: IR-coating ε ≤ 0.2; limited cavity → Ug ≤ 1.3 [VERIFY]) | |
| walls vs. ground/unheated | 0.30 | |
| floor build-up (warm side) | 0.50 | |
| ceiling vs. outside (replace) | 0.24 / 0.35 | |
| curtain wall / special glazing | 1.5 / 1.9 (special: R′w ≥ 40 dB, bullet, fire ≥18 mm: 2.0; glazing-only 1.6) |
Thin-layer rule (Dünnschichtregel): if the max practical build-up thickness is reached and λ ≤ 0.035 (blown/renewable 0.045) — the limit is waived. Modified residential single/dual buildings (small, ≤350 m², or short use): Qp ≤ 1.40·Ref (max +40 %) with H'T caps ~0.40–0.65 W/(m²K) by type [VERIFY table numbers]. Reference new-build comparison for planning: wall 0.28, roof 0.20, window 1.3 (g 0.60); primary-energy factors oil/gas 1.1, wood 0.2, grid power 1.8 (heading to 1.5 with the decarbonising mix — flips WP-vs-gas rankings [VERIFY]).
10.3 Element playbook (retrofit sequence: fabric → bridges → windows → summer → ventilation → plant)
- Single-leaf masonry: exterior WDVS (ETICS render-on-insulation — no
anchor penetrations through the insulation plane) or rear-ventilated rainscreen = easiest, moves the whole shell into the warm zone; interior insulation only with a hygrothermal proof (Glaser/dew-point inside the wall; GEG gives interior solutions a looser U target [VERIFY clause]) and with careful handling of timber beam heads (rot pocket § 8.6) and corner thermal bridges.
- WDVS + fire constraints: external wall finish classes follow the building
class — GKL4 non-loadbearing external walls A1/A2 or F30-B with surface layers (incl. insulation) ≥ B1; GKL5 surfaces B1; reaction classes A2-s1,d0… per EN 13501-1; tall/Sonderbau projects may demand A2 non-combustible lamellas or fire-break strips (lamellen-streifen) — coordinate with the fire skill; never bury combustible insulation without the surface-class chain intact.
- Two-leaf walls with cavity: blow-in (check debris + outer-leaf condition
first); already-filled cavity → external system or interior-proof route.
- Plinth/basement: perimeter insulation impossible post-hoc on precast tanked
walls; interior rigid boards (foam glass/XPS) on the cold side, impact-faced; treat cellar stairs and doors as envelope (frequently missed losses).
- Pitched roofs: between-rafter (needs rafters ≥18 cm, add under-rafter layer)
or over-rafter (best, only with re-roofing); historic decorated interiors → blown fibre from above + vapour-open underlay review.
- Flat roofs: 1930–60 warm-roof build-ups hold only 3–5 cm cork/EPS — today's
target ≈ 20 cm WLG 035 → verify dead load + snow + new falls (parapet raising drives cost); inverted roof (XPS above tanking) protects the membrane but the insulation must be closed-cell (wd class).
- Top-floor ceiling over unused attic (the cheapest tonne of CO₂): loose-fill
or laid boards ≥ 24–32 cm on the deck, walkway boards on top; pre-1960 timber joist floors U ≈ 0.8 or uninsulated 1.2–2 [VERIFY] → blow-in with moisture buffer respect (vapour-open from above?); 1960s concrete top slab U ≈ 1.3 → +12 cm meets limits; damp-proof course under loose fill.
- Cellar ceiling (over unheated): massive U ≈ 1.6 + 6 cm WLG035 from below is
compliant; Prussian-cap (Preußische Kappe) vaults → suspended ceiling + blown fibre; ground slab U ≈ 2.0 only insulates from above when the floor build-up is renewed anyway (+ damp-proof membrane).
- Windows: replacement is one measure, not the retrofit; Uw 1.3 (Ug ≈ 1.1 +
Uf ≤ 1.4 typical triple/good warm-edge double); reveals airtight-taped (three-joint rule — construction-detailing skill); new tightness → § 10.5; glazing-only swap (Ug ≤ 1.1) preserves heritage frames.
- Thermal bridges: balcony heads via connector elements (stainless/plastic),
wrap protruding slabs; ψ-simplified details per the thermal-moisture skill; the better U gets, the colder every bridge tip → mould risk moves to bridges, not the wall (fRsi check on the worst detail, § 9.1).
- Summer comfort is a retrofit side-effect: insulation + airtightness kill
night-cooling habits; dynamic overheat check (~1200 K·h residential [VERIFY]) → external shading (F_c ≤ 0.5, roller shutters best on old stock), internal mass, purge ventilation — plan WITH the envelope, not after.
10.4 Heat-pump retrofit flow-temperature strategy (services interface)
Sequence: heat load per room (not per building) → hydraulic concept (+buffer where radiators dominate or tariff lock-outs apply) → emitter check → valves/ heat-interface → hydraulic balance (Abgleich) → lower the flow target.
- Radiator enlargement vs. legacy 90/70 °C: to 70/55 ×1.5 area, 60/50 ×2,
55/45 ×2.5; 40–50 °C flow is the practical retrofit target with enlarged radiators; below ~40 °C pure convection collapses (fan-assisted or serial-flow units, or raise radiant share — UFH ≤100 W/m², design 35/25); >50 °C is fine for any HP but costs SPF.
- One-pipe (Einrohr) systems: replace fixed bypasses with load-dependent
adjustable ones, keep the ring ΔT constant in part load — or convert to two-pipe/Tichelmann per storey.
- DHW retrofit options: HP pre-heat + electric top-up (cheap, cycles summer);
HP + second boiler (space/emissions, keeps HP low-T); HT-HP direct (poor SPF); rooming-station fresh-water "small system" (hygiene-clean, trace-heated short legs); decentral instantaneous electric on long dead legs (3.5–27 kW). Legionella rules (§ W551 logic: 60 °C storage/3-l rule) constrain how low the DHW side may run [VERIFY].
- Bivalence: air-source monovalent to ≈ −16 °C is new-build only; bivalent-
alternative changeover ~50 % of max load → HP covers ~60 % of annual heat; bivalent-parallel with boiler at 50–70 % size is the old-radiator compromise. SPF anchors: air 2.7–3.2, ground 3.6–4.2, groundwater 3.8–4.6.
- Direct electric only where fabric ≥30 % better than reference (45 % if
replacing a hydronic system) or on grandfathered exceptions — the old night-storage floor circuits can often stay as load buffer with PV.
- Noise/source siting (air units, TA Lärm to property line, borehole permits/
VDI 4640 extraction values) per the services skill.
10.5 Ventilation after airtightness upgrade
Sealed windows + insulated envelope kill the old leak-based exchange → DIN 1946-6 moisture-protection level becomes mandatory. Retrofit standard: decentralised heat-recovery wall units (~120 m³/h class) — mould prevention independent of user behaviour; central Zu/Abluft = costly duct routes, reserve for vacated refurbishments; CO₂ demand control where occupancy fluctuates; air heating only below ~10 W/m² (fully modernised).
10.6 PV on existing roofs
Structural gate first: ballast vs. penetration-free framing, snow-clearance strip, roof remaining-life vs. ~25-a PV life (re-roof BEFORE mounting), flat-roof ballast loads vs. § 8.8 overload history. Tenant-electricity/building-supply models and state PV mandates (roof duties by Land, parking-lot PV) [VERIFY per site]; balcony-PV as low-threshold entry step.
11. Economics, whole-life and the keep-vs-replace decision
- Operation dominates: offices ≈ 75 % of lifecycle GHG arises in the use
phase (space heat/cool + electricity), residential ≈ 60 % — grey energy of a retrofit is repaid by operation savings that new-build demolition can never recover on short cycles. ~80–90 % of the buildings needed in 2045 already exist; building operation ≈ 35 % of final energy / ≈ 30 % of CO₂; the retrofit rate must double from ~1 %/a to ≥ 2 %/a [dated stock statistics — re-read].
- Cost logic: up to 80–85 % of whole-life cost arises AFTER construction;
operating costs historically equal the purchase cost after ~7 years [dated]; life-cycle accounting per VDI 2067 annuities (capital- + demand- + operation- bound; lifetimes: gas condensing ≈ 20 a, HP 15–20, pumps 12, UFH 30, radiators ~25 [VERIFY lossy table]). BEG subsidy demands better-than-code fabric; CO₂ price path 25 → 30 → 55 €/t (2025) then trading band — fossil operation is a rising annuity, model it.
- CRREM-style pathways: plot do-nothing vs. stepped retrofit emissions; the
crossing = stranding date (a 2006 hotel case stranded 2026 do-nothing, 2036 with two retrofit steps) — use it for sell/hold/refurbish decisions and DD.
- Material-side bonuses of keeping: brick ≈150-a service life, ~94 % of demolition
material recyclable; 1 m³ wood stores ≈0.5–1 t CO₂ (timber add-on storeys spare foundations and dodge demolition emissions); bio-based retrofits (hemp-lime spray 28–30 cm reaching U = 0.24 on a listed half-timbered wall; blown wood fibre on top floors) trade thickness for hygroscopic safety on old walls — a moisture argument, not only an energy one.
- Tenancy-law frame (residential): Modernisierung (energy upgrade) can be
passed into rent per law; Sanierung (defect repair) cannot — sequence and document measures so the distinction survives audit. DIN 31051 terms (Inspektion/Wartung/Instandsetzung/Verbesserung) vs. DIN 32736 Modernisierung in facility plans.
12. Decision tree (condensed)
Existing member / building in question├─ Lawful at erection & unchanged use? ── yes → Bestandsschutz: maintain to old rules;│ but Verkehrssicherungspflicht: inspection cycle § 3 stays, danger findings override├─ Change planned? (use ↑ / opening / add-on / new element)│ └─ yes → new parts per CURRENT code; affected path re-checked (Nachrechnung)│ ├─ qualified inventory feasible (cores+scans+records)?│ │ ├─ yes → modified γ (§ 4.6, authority agreement!) → utilisation│ │ └─ no → tabular historic strengths + full γ → utilisation│ ├─ util ≤ 1.0 & detailing OK & SLS (cracks/defl) OK → keep, monitor│ ├─ util 1.0–1.15 bending → Aufbeton/CFRP (§ 7.1/7.3)│ ├─ util column N↑ → jacket with OWN confinement hoops (§ 7.2)│ ├─ shear/punching deficit → bonded jackets/stirrup upgrade, re-check joint (§ 7)│ ├─ stability/bracing deficit → system change (§ 7.6) + foundation checks│ └─ bearing deficit → widen/underpin (§ 7.7) with Beweissicherung├─ Defects (corrosion/chloride/settlement/ASR)? dormant & repairable →│ Instandsetzung to old target state; active/structural → stop-use, expert└─ Energy/regulation drive → § 10 ladder (fabric → windows → ventilation → plant)with summer-comfort + moisture proofs per touched element
13. Recurring failure patterns in Bestand projects (what actually goes wrong)
- Statics on assumptions: no cores, no rebar scan → "as-drawing" d and cover lost
to leveling screeds → utilization errors > 15 %.
- Mixed code sets in one report (Mischungsverbot violation).
- Strengthening designed at mid-span, failing at the ends (jacket load transfer,
CFRP peel, topping joint shear — always check the ends first).
- New stiffness attracts new forces: an added core/bracing bay redistributes
everything; unreinforced old slabs as diaphragms crack at voids/openings.
- Stage loads forgotten (wet topping, slurry, jacking) and unloading ignored →
the strengthening only starts carrying after damage (pre-stress or prop it).
- Durability not re-established: repaired but still carbonated chloride-rich zone;
drainage left broken; vapour traps created by interior insulation without proof.
- Pollutants discovered during demolition (asbestos under the carpet, PCB in the
edge sealant) → stoppage + cost; § 3.3 testing is cheap.
- Fire downgrade by stealth: exposed steel jacket/CFRP in a former F90 zone;
WDVS surface class chain broken (A2-s1,d0 vs. B1 rules per GKL).
- Moisture regime shifted by energy retrofit (tight envelope, no ventilation
concept) → mould claims within one heating season.
- Settlement honesty missing: no pre-work neighbour documentation, then the 5 mm
"unavoidable" becomes a liability dispute.
- Over-strengthening: util-0.99 jackets everywhere erode robustness budgets and
cost; a monitor-first sequence often defers a third of the measures.
- Missing Bauwerksbuch update after works → next owner repeats the whole survey.
14. Verification checklist
Assessment phase:
- [ ] records set § 3.1 chased + missing-items log signed
- [ ] inspection category & cycle chosen (DIN 1076 / RÜV / VDI 6200 CC-RC)
- [ ] survey plan: zones, ≥3 rebar samples (≥5 per unknown zone), cores ≥3/zone,
carbonation+chloride profiles where XC/XD suspected; pollutant screening per § 3.3 periods with L2 follow-up where hit
- [ ] Beweissicherung (neighbour + own crack gauges) before any ground works
- [ ] as-built geometry captured (scan/survey), storey heights & slab thicknesses
Code path:
- [ ] Bestandsschutz classification A–C agreed in writing with owner/authority
- [ ] no mixed code sets; historic unit conversions documented
- [ ] modified-γ preconditions § 4.6 met AND agreed with Prüfingenieur
Verification:
- [ ] actions: target use categories, snow-zone audit, storage/rack/PV/greening loads
- [ ] member table: ULS + SLS (crack width where old 5‰ cap applies), as-built d
- [ ] detailing audit § 4.5 done (smooth-bar anchorage, stirrup absence, cranks)
- [ ] slender members: 2nd-order + K_r self-consistency (worked pattern § 6.2)
Strengthening:
- [ ] method chosen vs. deficit table § 7.8; ends/interfaces verified (joint shear,
load-introduction zones, peel/anchorage lines)
- [ ] all execution stages checked (including temporary supports)
- [ ] durability of new system: cover on new surface, adhesive temp class, drainage
- [ ] fire rating impact of every added/exposed element re-assessed
Monitor:
- [ ] gauges read-in schedule + re-inspection date in Bauwerksbuch; as-built of
strengthening handed over with materials' DoP/abP copies
15. FreeCAD / IFC workflow for existing fabric
- Scan-to-BIM intake: point cloud → reference in the model (IFC spatial zone
"Bestand" [VERIFY entity mapping in current exporter]); model measured as-built geometry, never nominal drawings; scan tolerances (±20–30 mm on old walls) feed the § 4.6 tolerance precondition check.
- Separate storey/phase for existing: model Bestand and Ertüchtigung in
distinct IFC stories/phases (Existing-Slab-L2, Retrofit-Topping-L2) with property sets carrying condition data: member key, fck,is source, util ratio, defect codes (S/D/V + Zustandsnote 0–4), last/next inspection — this keeps the Mischungsverbot visible in the model itself.
- Strengthening design: model composite sections (existing + topping/jacket) as
separate solids on one reference axis; drive the § 6.1 μ/ω checks from a linked spreadsheet so every survey correction re-runs cheaply; coordinate service penetrations against rebar-scan zones before coring.
- Cross-reference: IFC exchange requirements, naming, MVD choice and curation
cadence live in the bim-management skill; reinforcement-scan data hand-off format in concrete-detailing; structural-section setup in structural-analysis; U-value/blower-door models in building-physics-thermal-moisture.
16. Component reuse & circular deconstruction (Wiederverwendung von Bauteilen)
[Digested from Kompendium Nachhaltige Bauwerke – Hochbauten, Springer 2026, Ch.32 (Forschung: Wiederverwendung von Stahlbetonbauteilen) — research-level, not yet a harmonized code; VERIFY current guideline status before relying on any number here in a submittal.]
This is a different workflow from § 7 strengthening: instead of upgrading an existing member in place, you are qualifying a donor member (from this building or another) for reuse as a structural component elsewhere. Treat it as an additional gate before demolition sign-off, not an afterthought once a building is already scheduled for the crusher.
17.1 5-class reusability system (Küpfer & Fivet 2023)
| Class | What survives | Reuse route | |
|---|---|---|---|
| 1 | Component group, connections preserved, existing rebar statically usable, no/minor damage | Direct reuse (group), highest value | |
| 2 | Like 1 but connections not preserved | Individual component reuse | |
| 3 | Only concrete compressive strength usable; rebar not statically creditable | "Weiterverwendung" as blocks/whole elements (non-structural credit for the steel) | |
| 4 | Demolition + recycling | Aggregate compressive strength only (RC-aggregate, ballast, backfill — cross-ref building-materials recycled-aggregate rules) | |
| 5 | Demolition + disposal | No recycling possible (contamination, e.g. asbestos) |
Two operating scenarios: direct extraction from a single donor building (iterative design coordinated with the client, components go straight to the new project) vs. pooled storage/warehouse (standardized modules held for future demand — needs a Standard-ID/QR-code and issued test certificate per element).
17.2 3-stage investigation process
- Screening: visual/dimensional survey + archival document chase (same
record sources as § 3.1) — first pass at class assignment.
- Detailed survey: full geometric/material survey, preliminary class
assignment, contamination screening (§ 3.3 periods apply), deconstruction concept drafted.
- Final testing: geometry, mechanical properties and damage tested on the
actually recovered elements (not just predicted from the donor building) — issue test certificates (origin + measured properties) before the element is released for reuse design.
17.3 Modified partial safety factors for reused elements (APFM)
The Adjusted Partial Factor Method (fib Bulletin 80, 2016) lets γc and γs be reduced below the new-build defaults when the measured coefficient of variation on the salvaged elements is lower than the new-build assumption used to derive those defaults — more data (destructive + non-destructive testing on the actual donor elements) buys a smaller safety margin, while holding the same target reliability index β = 3.8 (CC2, DIN EN 1990). Order of magnitude: γc reducible by up to ≈10 % under low scatter; γs reduction is much smaller (steel properties are already tightly controlled at manufacture, so there is less "unknown" to buy down with testing). This is the analytical route that makes class-1/2 reuse economically viable instead of over-conservative — do not default to full new-build γ-factors on tested salvaged material, but do not invent a reduction without the underlying test programme either.
17.4 Sustained-load caveat (αcc for old concrete)
The standard German NA value αcc = 0.85 (reinforced) / 0.70 (unreinforced) per DIN EN 1992-1-1 bakes in a post-hardening strength benefit that is real for young concrete (concrete gains ≈75–80 % of its long-term sustained strength within days-to-weeks of loading, Rüsch 1960) but may not still apply to old concrete recovered decades later, because that post-hardening window has long since closed. Tests on 52-year-old core samples (from a retaining wall) loaded to 62–82 % of mean strength for up to 70 days showed only ≈70–75 % sustained-strength ratio — i.e. αcc = 0.85 can overestimate capacity for old/ existing concrete. Treat this as a flag to discuss with the Prüfingenieur on any reuse or Nachrechnung (§ 4) job with concrete older than ~40–50 years, not as a ready-made reduced αcc value — testing on the specific donor concrete is the only way to quantify it for a given project. [Further testing on 1990s wall elements and a 1966 prestressed bridge near tendons was ongoing at source publication — check for a published follow-up before citing a specific number.]
17.5 Dry-joint friction in reused unreinforced concrete (first dedicated tests)
Mecka et al. 2025, specimens from a 1972 C45/55 riverbank wall, in-plane (pure shear) and out-of-plane (bending+shear) tests, sawn (smooth) vs. shot-blasted (rough) joints, 6 tests each:
- Sliding friction coefficient at 17.8 MPa normal stress: up to 0.68
(shot-blasted, in-plane) vs. 0.56 (sawn, in-plane).
- Static friction coefficient stays roughly constant at ≈0.4–0.5 regardless
of surface treatment; sliding friction increases with compressive utilisation then drops slightly at very high loads (micro-spalling at the joint face).
- Smooth (sawn) joints reach high friction early at small displacements but
fail brittle/suddenly under bending (out-of-plane) — suited to combined bending+shear connections where a stiff, low-slip joint matters more than ductility.
- Rough (shot-blasted) joints are more ductile under pure shear (in-plane)
but weaker under bending because the joint-gap opening reduces effective contact — suited to pure-shear modular connections, not bending-dominated ones.
- Headline: **joint friction in old unreinforced concrete measures significantly
lower than literature/code assumptions for new construction joints** — component-specific testing is required before crediting friction capacity in a reuse connection design; do not carry over a new-concrete Reibungsbeiwert.
17.6 Deconstruction / separation method choice (per DIN 18007)
| Method | Resulting joint surface | Suited to | Relative cost | |
|---|---|---|---|---|
| Sawing (band/diamond-chain/rope/wall saw) | Clean, smooth | Combined bending+shear connections (§ 17.5) | € | |
| High-pressure water (cutting or jetting) | Uneven-to-rough (jetting rougher) | Shear-only connections when rough | €€ | |
| Press-splitting | Heavily interlocked, needs rework; can plastically deform donor rebar | Special cases only | €€€ | |
| Oxygen lance | Thermally damages near-surface microstructure | Underwater/confined spaces only | €€€€ |
Sawing and high-pressure water are the default choices (handling, output, cost); reserve press-splitting and oxygen-lance for the special cases their column names — never pick a method by habit when the joint's structural role (§ 17.5) should drive it.
17.7 Design-for-disassembly process note
A reuse project does not fit the standard German HOAI waterfall (design detail is needed too early for reused-component decisions, which depend on what a donor building actually yields). The literature proposes an agile/iterative loop through LPH 0–5: requirements workshop up front, iterative LCA/LCC refinement each loop, ending in logistics/installation planning + QA — and flags that this needs a different contract model (pre-construction/consulting agreements) because standard HOAI fee structure does not map cleanly onto iterative reuse design work. Flag this to the client/PM early — a reuse component strategy decided at LPH 3 like a normal material choice arrives too late to actually secure the donor elements.
17.8 CO₂ savings (context for the business case)
Component reuse reports 40–80 % CO₂ savings vs. conventional new build, depending on component type, transport distance and repair effort; cut/reused cast-in-place slabs specifically reach up to 85 % reduction (Küpfer et al. 2023/2024). Use these as order-of-magnitude business-case numbers, not project-specific LCA substitutes — run the actual A1-A3+transport comparison per sustainable-construction for a real number.
17. Related skills
- Structure:
structural-analysis(altered systems, 2nd order),concrete-detailing
(post-installed anchors § 7.4, carbon-reinforced overlay § 7.3), masonry-construction (Ringanker, repointing), timber-steel-design (member strengthening), seismic-design (ductility upgrade shares the § 7.6 logic).
- Ground & envelope:
geotechnics-foundations(§ 7.7),roofing-waterproofing
(§ 10.3 roofs), building-physics-thermal-moisture (Glaser/interior-insulation proofs § 9 and § 10.3).
- Services & compliance:
building-services-tga(§ 10.4–10.5),
fire-protection-building (§ 10.3 fire constraints), cost-management-din276 (§ 11 LCC), bim-management (§ 15 phase/condition data).
- Circular/reuse:
sustainable-construction(whole-project LCA/circularity
framing, material passports), building-materials (recycled-aggregate concrete rules for Class-4 material, § 17.1).
Norms referenced (edition check at use): DIN EN 1990/1991/1992 (+NA), DIN 1045 series incl. 1045-2/1045-3, historic DIN 1045 (1972/1978/1988) and GDR TGL/ETV sets, DIN EN 12504 / 13791 / 206 / 13670, DIN 1076 + RI-EBW-PRÜF, RÜV, ARGEBAU Bestand notes, VDI 6200, VDI/GVSS 6202-1, DIN 4123, DIN EN 1997-1, DAfStb guidelines (bonded reinforcement, load tests, jackets), GEG/GModG, DIN 4108 series, DIN EN 12831, VDI 2067, VDI 4640, DIN V 18599, DIN 1946-6, DIN 4109. All values are planning aids; [VERIFY]-tagged items and final designs must be confirmed against the texts in force by an authorised professional.