version: "1.0.0" name: feature-progress-tracking description: > Keeping a feature's state true while it is being built: one status per resource with defined transitions, a validation line required before anything reaches done, and a persisted record current enough that another agent or another session can resume from it without asking. Use when a feature spans more than one sitting, when someone else may pick the work up, when the answer to "where are we" is a summary of the conversation, when resources are marked done because code was written for them, when a blocker has been open long enough that nobody remembers what it needs, or when a plan and the code have silently diverged. Does not implement the resources (feature-execution), does not decide what counts as a resource (feature-decomposition), and does not perform the final review (feature-readiness-review).


Feature Progress Tracking

Purpose

Durable records preserve evidence and unfinished work across handoffs. Reconstruction is possible from diffs, logs and test results, but uncertainty must remain visible; do not invent start times or past validation merely to complete a table.

This skill exists so that a second agent, opening the repository with no history, can read one entry point and find the current state, supporting evidence and next ready work.

The status set

StatusMeansEntered when
TODODefined, not startedThe resource is created
IN_PROGRESSStarted, with implementation or validation remainingWork starts; may be paused for handoff
BLOCKEDCannot proceed for a reason outside the workThe blocker is identified
DONEImplemented and validatedThe validation ran and passed
SKIPPEDDeliberately not done in this feature; still wantedA decision, with a reason and an owner
CANCELLEDResource retired: no longer needed or replacedReason and retained scope are recorded

Common transitions (additional evidence-based transitions are described below):

text
TODO ──► IN_PROGRESS ──► DONE
│ │ ▲
│ ▼ │
│ BLOCKED
│ │
├──► SKIPPED ◄┘
└──► CANCELLED
DONE ──► IN_PROGRESS when evidence or a change invalidates completion; record why

The normal path is TODO → IN_PROGRESS → DONE. A direct TODO → DONE transition is acceptable for an atomic task completed and validated between observations; record the validation rather than inventing historical states. BLOCKED normally returns through IN_PROGRESS, but the blocker may also make the resource CANCELLED or prove that no work remained. DONE still requires valid acceptance evidence, even when a resolved blocker needs no new code. State transitions serve truthful resumption, not workflow accounting for its own sake.

Workflow

  1. Reuse the established tracking location and record format. The table and log are roles,

not mandatory separate files. Create entries when resources are defined, initially TODO for unstarted work. When tracking begins later, reconstruct only evidence-supported state and label unknowns.

  1. Update at durable handoff points and material transitions. For multi-session or parallel

work, update before ownership changes and before ending a session. Do not turn sub-minute local edits into an event stream that costs more than the work.

  1. Require relevant acceptance evidence for DONE. Link what ran, results and the checked

code/contract revision and environment; a command name alone is not a passing result. Keep enough durable evidence in the established record for the next owner to substantiate that status. A mutable "latest" badge or expiring artifact link alone is insufficient. If an artifact becomes unavailable, assess the remaining evidence before reopening affected work; losing a link does not prove that the check failed or never ran.

  1. Record a blocker's question or missing condition, affected work, resolution owner,

evidence needed to unblock, and what continues meanwhile. If the owner is unknown, say so instead of assigning decision authority by assumption.

  1. Append to the execution log on start, completion, blocking, unblocking and any plan

change. The log is append-only; a correction is a new entry.

  1. Leave the files true at the end of every session, whatever state the work is in.
  2. Track revision impact. Record the Product/Engineering or Tech baseline and plan revision. When

either changes, trace the actual acceptance, implementation and evidence impact. Reopen RES-* and mark EV-* stale only where their coverage is invalidated; a new revision label or reordered plan alone does not invalidate a passing check. Name what triggered each state change.

Load artefact formats when creating or resuming records, or when evidence access or retention puts a completion claim in doubt.

Decision rules

text
IF a resource has been implemented but not validated
THEN it is IN_PROGRESS, or BLOCKED when an external impediment prevents required validation.
Record implemented work and missing evidence; do not call it qualified DONE.
IF validation was run and something failed
THEN investigate the cause; an implementation defect stays IN_PROGRESS, an external
impediment can be BLOCKED. A required failing check does not support DONE.
IF a resource is DONE and a later resource breaks it
THEN it returns to IN_PROGRESS, and the log says which resource reopened it.
IF an accepted baseline or CT-* changes
THEN trace the impact to RES-*/EV-*, reopen affected rows, and preserve unaffected DONE evidence.
IF a resource is skipped or cancelled
THEN record who decided, why and which commitments remain. Neither status amends
Required scope: link equivalent accepted coverage or an authorized scope/acceptance revision;
otherwise report the feature incomplete against that commitment. Reuse existing authority.
A replacement still awaiting validation remains open under its own ID.
IF the same resource has been IN_PROGRESS across three sessions
THEN inspect remaining work, session length and dependencies. Split only when useful;
session count alone proves neither oversizing nor an external blocker.
IF the progress file and the code disagree
THEN reconcile accepted scope, code revision and evidence before changing state. The tracker
may be stale, the implementation may have regressed, or a supersession may be missing.
Record what was established and reopen affected work; do not rewrite acceptance to fit code.
IF the feature is Light/Inline
THEN keep proportionate inline status; do not create a dossier for ceremony. If work must cross a
session or owner, change persistence to Dossier and preserve the current state before handoff;
this alone does not increase technical depth.

Constraints

  • Make concurrent ownership explicit. In one shared working tree, coordinate an editor for

the shared snapshot/log or use separately owned records with an explicit merger. Git merge conflicts do not protect against one writer overwriting another's uncommitted file updates. With separate working trees, merge changes and reconcile status, dependencies and evidence even when no textual conflict occurs. Ownership is a coordination rule, not a filesystem lock; inspect fresh state before updating and preserve other owners' changes.

  • Never mark DONE optimistically. "It should work" is IN_PROGRESS with a note.
  • Preserve resource identity and history. Never delete a row or reuse its ID for a different

obligation. For an accepted split/merge, link old and new IDs, the reason and updated dependencies; retire replaced rows as CANCELLED with replacement links, without implying their obligations vanished. Derive each resulting status from its actual scope and valid evidence; do not copy a parent's DONE onto unverified children or reset unaffected completed work. Keep prior states and evidence in history.

  • Preserve decision history. Append corrections, identify actor/resource/revision, and

distinguish event time from recording time. Concurrent wall-clock order is not dependency order. Avoid secrets and personal payloads; if sensitive material was recorded, follow the repository's redaction procedure and retain a sanitized correction trail.

Output

The progress table, current, and the report derived from it:

text
Feature Asynchronous order dispatch
Resources 10 total — 4 DONE, 1 IN_PROGRESS, 2 BLOCKED, 2 TODO, 1 CANCELLED
Blocked on Q-08 (uniqueness scope for the idempotency key), asked 2026-09-05
Next RES-09 (metrics), unaffected by the blocker
Plan changes RES-06 added 2026-09-05; RES-11 cancelled 2026-09-04

Keep the report proportionate; include material validation gaps and changed assumptions when the five-line summary would hide them. Resource counts are not effort percentages or release readiness.