Manage construction contract administration from the field perspective. Covers AIA contract forms (A101, A201, A401), bond types and requirements, mechanics lien law, insurance verification, indemnification, dispute resolution, and subcontractor default procedures. Provides practical field guidance for notice requirements, lien waiver processing, COI verification, and claims documentation. Integrates with pay-application (lien waivers), change-order-tracker (constructive changes), delay-tracker (notice provisions), sub-performance (default triggers), and cost-tracking (back-charges). Triggers: "contract", "contract admin", "AIA", "A201", "A101", "bond", "performance bond", "payment bond", "lien", "lien waiver", "mechanics lien", "insurance", "COI", "certificate of insurance", "OCIP", "CCIP", "indemnification", "dispute", "mediation", "arbitration", "notice", "cure notice", "default", "sub default", "termination for cause", "claims", "ConsensusDocs", "EJCDC".

Install

npx vskill@latest install fdu-ins/insurance-skills/contract-administration

SKILL.md

The same SKILL.md was published earlier as fdu-ins/insurance-skills/contract-administration.

Contract Administration Skill

Overview

The contract-administration skill provides construction superintendents with practical, field-level guidance on contract administration tasks that directly affect daily operations. This is not a law school course -- it is the working knowledge a superintendent needs to protect the project, keep subcontractors accountable, process pay applications correctly, and avoid the costly mistakes that happen when field personnel do not understand the contract documents sitting in the job trailer.

Why superintendents need this:

  • You sign daily reports that become evidence in claims and disputes
  • You accept or reject work that triggers payment obligations
  • You direct subcontractors under contracts you may not have read cover-to-cover
  • You are the first person to notice when a sub is failing, and the documentation you create (or fail to create) determines whether the project can terminate for cause or is stuck
  • Your verbal directives can create constructive change orders worth hundreds of thousands of dollars
  • Missing a notice deadline by even one day can waive the project's right to recover time or money

What this skill covers:

  1. AIA contract forms that govern most commercial construction
  2. How ConsensusDocs and EJCDC contracts differ (so you are not blindsided)
  3. Bond types, requirements, and claims processes
  4. Mechanics lien law and lien waiver processing
  5. Insurance requirements and COI verification
  6. Indemnification clauses and what they mean in the field
  7. Dispute resolution procedures from notice through arbitration
  8. Subcontractor default procedures from warning signs through replacement

Critical principle: In contract administration, written notice is everything. Verbal conversations do not preserve contractual rights. If it is not in writing, it did not happen.


AIA Contract Forms Field Guide

The American Institute of Architects (AIA) publishes the most widely used standard contract forms in commercial construction. Three documents form the backbone of most projects.

A101 -- Owner-Contractor Agreement

The A101 is the main agreement between the owner and general contractor. It establishes the deal: scope, price, time, and payment terms.

Key Clauses for Field Operations
ArticleSubjectWhat the Super Needs to Know
Art. 3Date of Commencement & Substantial CompletionYour schedule is contractually bound to these dates. Substantial Completion triggers retainage release, warranty periods, and liquidated damages cutoff. Know these dates cold.
Art. 4Contract SumThe total price. Every dollar above this requires an approved change order. No verbal authorizations.
Art. 5Progress PaymentsPay application schedule (monthly, Net 30 per W Principles standard), retainage percentage (W Principles default: 10% flat), and conditions for payment. The architect certifies payment -- you provide the supporting documentation.
Art. 6Dispute ResolutionSpecifies whether disputes go to mediation, arbitration, or litigation. Check this BEFORE you have a dispute.
Art. 7Termination or SuspensionOwner can suspend work for convenience; contractor can stop work if payment is 7+ days late (after 7-day written notice).
Art. 8MiscellaneousInsurance requirements, key personnel, governing law.

Field Impact: The A101 sets the financial and time boundaries. When someone on site says "the owner told us to go ahead with the extra work," your response is: "Show me the signed change order or written authorization per Article 4."

Common Pitfalls
  1. Starting work before Notice to Proceed (NTP) -- Work performed before NTP may not be compensable
  2. Missing Substantial Completion criteria -- Review the definition; it is not "we think it is done" but rather "the owner can use it for its intended purpose"
  3. Retainage math errors -- Track retainage held vs. retainage due on every pay application
  4. Liquidated damages ignorance -- Know the daily LD rate; it starts accumulating the day after Substantial Completion deadline
A201 -- General Conditions of the Contract for Construction

The A201 is the most important document for daily field operations. It contains the rules of engagement for how the project is built, administered, and disputes are resolved. Every superintendent should read Articles 3, 4, 7, 8, 9, 12, 14, and 15.

Article 1 -- General Provisions
SectionSubjectField Relevance
1.1.1Contract Documents definedDrawings, specs, A101, A201, addenda, modifications. All carry equal weight -- specs do not override drawings or vice versa.
1.2Correlation of DocumentsIf something is shown on drawings but not in specs (or vice versa), contractor must provide it. This prevents "I did not see it in the specs" arguments.
1.5Ownership of DocumentsDrawings belong to the architect. You can use them for this project only.
Article 2 -- Owner Responsibilities
SectionSubjectField Relevance
2.2Evidence of Financial ArrangementsContractor can request proof that the owner can pay. Use this if you suspect owner financial trouble.
2.3Information and ServicesOwner must provide surveys, legal descriptions, utility locations. If owner data is wrong and it causes delay or extra cost, that is an owner-caused issue.
Article 3 -- Contractor Responsibilities
SectionSubjectField Relevance
3.1.1General dutyContractor shall perform work "consistent with the Contract Documents and reasonably inferable therefrom." The word "reasonably inferable" means you cannot claim ignorance of something obvious even if it is not explicitly shown.
3.2Review of DocumentsContractor must review documents and report errors or inconsistencies. Failure to report a noticed error can shift responsibility to contractor.
3.3Supervision and Construction ProceduresContractor is solely responsible for means, methods, techniques, sequences, and procedures. The architect cannot tell you HOW to build -- only WHAT to build.
3.4Labor and MaterialsContractor furnishes all labor, materials, equipment. Unless the contract says "Owner furnished," you provide it.
3.5WarrantyContractor warrants materials and workmanship free from defects and conforming to contract documents. This is not a time-limited warranty -- it covers the entire construction period.
3.7Permits, Fees, NoticesContractor obtains and pays for permits (unless contract says otherwise). You must comply with all codes regardless of what the drawings show. If code conflicts with drawings, notify the architect.
3.9SuperintendentContractor shall employ a competent superintendent who shall be present on site at all times work is being performed. The super represents the contractor in the field and is authorized to receive communications.
3.10Contractor's SchedulesMust submit schedule promptly after contract execution and update regularly. Schedule must conform to contract time limits.
3.12Shop Drawings and SubmittalsContractor reviews submittals for compliance before sending to architect. Architect review does not relieve contractor of responsibility for errors in submittals.
3.18IndemnificationContractor indemnifies owner and architect for claims arising from contractor's negligent acts or omissions. This is the key liability clause -- see Indemnification section below.
Article 4 -- Architect's Role
SectionSubjectField Relevance
4.2.1AdministrationArchitect administers the contract, visits site, keeps owner informed. Architect does NOT supervise construction -- that is the contractor's job.
4.2.6Rejection of WorkArchitect can reject work that does not conform to contract documents. This can happen at any time, even after you think the work is accepted.
4.2.7SubmittalsArchitect reviews submittals for "limited purpose of checking for conformance with information given and the design concept." This is not a comprehensive check -- contractor retains responsibility.
4.2.11-14Initial Decision MakerArchitect serves as the Initial Decision Maker (IDM) for claims and disputes. Claims must go through the architect before mediation or arbitration.
Article 7 -- Changes in the Work
SectionSubjectField Relevance
7.1GeneralChanges only by Change Order (signed by owner, contractor, architect), Construction Change Directive (CCD, signed by owner and architect), or minor change order (architect alone for changes not affecting cost or time).
7.2Change OrdersMust be signed by all three parties. No verbal change orders. Period.
7.3Construction Change DirectivesOwner and architect can direct changes even without contractor agreement on cost/time. Contractor must proceed with the work. Cost determined later by: mutual agreement, unit prices, cost-plus, or architect's determination.
7.4Minor ChangesArchitect can order minor changes consistent with intent of contract documents, not involving cost or time adjustment. If you think a "minor change" actually affects cost or time, object in writing immediately.

FIELD CRITICAL: If someone verbally directs you to do something different from the drawings, respond:

  1. Acknowledge the request
  2. State that it requires a written change directive or change order
  3. Send written confirmation of what was requested (email is acceptable)
  4. Do NOT proceed until you have written authorization unless the CCD process applies
Article 8 -- Time
SectionSubjectField Relevance
8.1.1Time definitions"Date of Commencement" starts the clock. Know this date.
8.2.1Progress and CompletionTime limits are "of the essence." This legal phrase means deadlines are strict -- missing them is a material breach.
8.3Delays and ExtensionsIf contractor is delayed by owner, architect, or separate contractor, contractor is entitled to time extension. BUT: contractor must submit a claim per Article 15 -- the extension is not automatic.
Article 9 -- Payments and Completion

This is the start of the file. Read the full SKILL.md on GitHub.

Security

  • Security scanPassed, 95 of 100Pattern checks on the skill's files.
  • Model reviewPassed

Quality evaluation

  • Task evaluationNot runNo evaluation yet. Run one in Skill Studio.

Source

Popularity

Repository stars
75
Repository forks
19
7-day trend score
22

Stars and forks are for the whole GitHub repository, not this skill alone. Not refreshed yet.

Works with

Any agent vskill installs to: 56 targets in all. These 39 have a page on this site.

  • Claude Code
  • Cursor
  • GitHub Copilot
  • Windsurf
  • Codex
  • Gemini CLI
  • Cline
  • Amp
  • Roo Code
  • Goose
  • Continue
  • Kilo Code
  • Junie
  • Trae
  • OpenHands
  • Qwen Code
  • AI Agent
  • Tabnine Chat
  • Sourcegraph Cody
  • Amazon Q
  • Firebase Genkit
  • Sweep
  • Devin
  • Phind
  • Mentat
  • Claude Desktop
  • Aider
  • GPT Pilot
  • Plandex
  • bolt.new
  • v0
  • Replit Agent
  • Anse
  • TypingMind
  • BetterChatGPT
  • LibreChat
  • Warp AI
  • Pieces