Bauen im Bestand (working with existing structures) for DACH practice: condition assessment workflow (Dokumentation, Bestandsaufnahme, Voruntersuchung, Bauwerksprüfung with DIN 1076 cycles — Hauptprüfung 6 a / einfache Prüfung 3 a / Beobachtung, S/D/V Zustandsnote 0–4, RÜV and VDI 6200 CC/RC inspection cadence); material testing (reinforcement induction scan, half-cell potential, phenolphthalein carbonation, chloride profiles, Rebound ≥9 readings, cores per DIN EN 12504/13791 with 5%-fractile s…

Install

npx vskill@latest install felixkarevo/construction-skills/existing-structures-retrofit

Semi-extensibleMentions customization, but needs skill-specific knowledge. Read the extensible skills standard

SKILL.md

The same SKILL.md was published earlier as felixkarevo/construction-skills/existing-structures-retrofit.

Existing Structures & Retrofit (Bauen im Bestand) — DACH Practice Skill

Simple-first gate (governs how this skill is applied). Default every choice here to
the simplest proven solution at the agreed standard tier — see the governing skill
simple-first-building (complexity ladder §1). Escalate to more demanding construction
(innovative systems, one-off details, higher comfort tiers) only when the client
explicitly asks for it, with cost/schedule impact stated; deviate below the usual
standard or the aarRdT only via the documented risk-acceptance machinery
(simple-first-building §3) — public permission never cures the private default.

Agent-neutral procedure skill for assessing, re-checking and strengthening existing buildings (and for deciding whether to), under the German-language regulatory and normative framework. German terms are kept in parentheses because inventories, Prüfberichte and submissions circulate in German.

Scope. Reinforced concrete / masonry stock of the 20th century is the core (worked examples follow it); timber and steel defect logic is included at assessment level. Bridges/civil works appear only through the inspection machinery (DIN 1076) that building practice borrows. Energy and services retrofit is covered to the interface where the building-physics, TGA and fire skills take over.

0. How to use this skill — and the [VERIFY] convention

Use this skill when the task involves ANY of:

  • converting/intensifying use of an existing building (living→office, add-on storey, new

openings),

  • re-checking (Nachrechnung / Nachweis im Bestand) old members against current rules,
  • planning strengthening (Aufbeton, jackets, CFRP, added walls, underpinning),
  • diagnosing defects (cracks, spalling, corrosion, damp, mould, settlement),
  • condition survey programmes and inspection cycles for owned/municipal stock,
  • deciding retrofit vs. demolish, with whole-life numbers,
  • modelling existing fabric (scan-to-BIM) for any of the above.

[VERIFY] convention. This skill is distilled from standards-adjacent references; some source tables arrived lossy. Any figure or rule marked [VERIFY] must be re-read in the current norm text (DIN EN 1990/1992, DIN 1045-2, DIN 1076, VDI 6200, GEG in force at project date) before it goes into a calculation report. Unmarked values are safe to use as planning figures; final design remains the job of a licensed Tragwerksplaner, and re-checks in Germany are coordinated with the Prüfingenieur für Standsicherheit / building authority early.

Hard limits of this skill: it never replaces a Voruntersuchung by qualified persons, never certifies Standsicherheit, and treats pollutant findings as triggers for specialist measurement (Schadstoffkataster), not as clearance.

1. Master sequence: assess → define target → verify → strengthen → monitor

Every Bestand project runs the same five phases; skipping or overlapping them is the root cause of most retrofit failures.

PhaseGermanOutputTypical trap
1 AssessBestandsaufnahme / Voruntersuchungdocumented condition + material data + defects + pollutantsbuilding on drawings alone; no cores; no crack mapping
2 TargetZieldefinition / Nutzungsänderungload model, target utilization, residual life, service classauthority/owner expectations not fixed before measuring
3 VerifyNachrechnung / Bewertungutilisation per member, code path (Bestandsschutz vs. new rules)mixing code generations; ignoring old detailing rules
4 StrengthenErtüchtigung / Instandsetzungmethod choice with force-transfer details, staging checkscomposite-interface shear forgotten; load-introduction zones
5 MonitorBeobachtung / Bauwerksbuch updategauges, re-inspection cadence, documented as-built change"repaired and forgotten"; no follow-up cycle

Stock context that makes this discipline worth it: roughly 10 % of dwellings are younger than 15 a, about 60 % were built before 1960, and of refurbishments only ~25 % are driven by repair need while ~75 % are driven by change of use (Nutzungsänderung). A re-check that cannot prove the existing member under the NEW use will end in strengthening — plan for it.

Vocabulary (DIN EN 1990 / industry usage, keep them apart in reports):

  • Instandhaltung — maintenance: preserves the target state (inspect, service).
  • Instandsetzung — repair: restores the target state after damage (same design

goals).

  • Ertüchtigung — upgrade: raises the target state above the original (new loads,

new code level, strengthening).

  • Nachrechnung — re-check: proof of an existing structure under CURRENT rules,

with code-permitted relaxations where the standard allows.

  • Bestandsschutz — grandfathering: lawfully-erected fabric may remain even if

today's rules differ (§ 2).

  • Nutzungsdauer / Lebensdauer — design working life (DIN EN 1990: 50 a for

buildings, 100 a for monumental/bridge-type structures) vs. actual service life.

  • Mischungsverbot — do not mix code sets within one verification; exception:

non-monolithic precast joints transmitting only support forces.

2. Code path: Bestandsschutz, change of use, and the Nachrechnung transition

2.1 Bestandsschutz (grandfathering) — what survives and what breaks it

Principle: a structure lawfully erected and maintained under the rules of its time may remain, even though it would not be approved today. Repairs may follow the old rules. Preconditions, all three:

  1. original lawfulness (Baugenehmigung, conformity at erection),
  2. no substantial change (keine wesentliche Änderung),
  3. condition as intended at erection — normal wear only.

Bestandsschutz is lost where there is danger to life/health, or where the intervention reaches the quality of a new building. Loss also never covers damage that arose from a rule now known to be insufficient (example in the case law tradition: overhead single-pane glazing ESG→VSG must be upgraded even on repair).

Authority levers (MBO logic, adopted into Landesbauordnungen):

  • Anpassungsverlangen (§85(1)5 MBO) — authority may demand compliance to

current requirements where a concrete danger exists; burden of proof on the authority. Health-hazardous products (e.g. asbestos in reachable condition) can trigger replacement even of untouched parts.

  • Harmonisierungsverlangen — on a substantial change, directly adjacent

constructive-related parts may be pulled up to current rules if no unreasonable extra cost results (e.g. a new stair may pull the adjacent landing and stair enclosure up to current rules).

  • Intervention grading (stages A–C): A = renewal of defective parts with same

use, substance not destroyed → procedure-free; C = interventions so deep that a whole-building proof is triggered. Classify the planned work early.

2.2 Change-of-use / alteration rules that drive the statics
  • Durchbrüche (new openings): local compensation per CURRENT rules (e.g. RC

frame action); no whole-building current-rule proof triggered by the opening.

  • Umbau storey loads: load path of NEW or altered elements per current code;

existing parts may keep the historic verification and merely carry the added loads; any strengthening member is designed to the new code.

  • Aufstockung (add-on storey): the added loads per current actions standard

must be carried; unchanged lower parts are proven under the ORIGINAL code including the new loads; if lower storeys would need substantial change anyway, the whole building is treated as a new build.

  • Later "neue Erkenntnisse" (corrected old rules) can reopen the historic proof.
  • New products (retrofit adhesives, FRP, grouts) always need current conformity

route (CE / abZ / ZiE) — grandfathering never covers them.

2.3 Nachrechnung: existing-code → EC2/DIN EN 1992 transition

Two-stage material assessment is the standard route: (1) derive nominal strengths from documents/historic code tables, (2) upgrade by testing where needed. The transition vocabulary old↔new must be exact in the report:

  • σ-Verfahren (working stress) until 1972 in West Germany; **Traglastverfahren

(ultimate load)** introduced in the GDR from 1955 with a global η factor — GDR-era calculations are NOT directly comparable to EC2 utilization.

  • 1972 DIN 1045: strength classes Bn50–Bn550 as 5 % fractile 28 d cylinder, design

value = β·Nennwert with global safety η; 1978 units switched N/mm²; 2001/2011 C-classes (EN 206).

  • Concrete and steel partial factors may be reduced for the re-check of

existing RC if a qualified inventory exists (§ 4.7 modified γ table and its preconditions). Without qualified inventory, full current factors apply and the tabular historic strengths (§ 4.5) govern.

3. Documentation and survey programme (Bestandsaufnahme)

3.1 Paper/digital records to chase before any drilling

Checklist (as-found documentation set):

  1. ownership + land survey (Lageplan), permits (Baugenehmigung incl. old annexes),
  2. as-built statics: structural calculations, reinforcement plans/Barroschauen,

formwork plans, precast connection drawings,

  1. TGA as-builts, facade/waterproofing documentation, expert reports, test fields,
  2. utility routes and Kampfmittel (UXO) records, maintenance logs / Bauwerksbuch,
  3. records of changed actions: groundwater level shifts, adjacent excavations,
  4. events: fire, storm, flood, mining subsidence, earthquakes,
  5. alteration history (changes of use, added loads: racks, machines, PV, greening),
  6. neighbour situation (Beweissicherung — documented adjacent-condition).

Missing records are the normal case for pre-1960 fabric and force the testing route of § 4. The documentation set closes with a Bauwerksbuch-style conformity summary.

3.2 Physical survey methods (selection by question)
QuestionMethodNotes from practice
rebar position/diameter/coverinduction scanning / cover meterdestructive confirmation on anchorage zones
carbonation depthphenolphthalein on fresh fractureuncarbonated = red; carbonated stays colourless below pH≈9
chloride contentpowder from ground profiles, wet chemistry / potentiometric titrationprofile vs. depth, not single surface value
corrosion activityhalf-cell potential mappingindications, not quantification
concrete strengthRebound (Schmidt) and/or coresRebound supplementary only; cores per § 4.6
crack widthcalibrated loupe / gaugemap plan + elevation, mark active-crack monitors
crack depthcore or ultrasonic across crack
voids/laminations masonrytap test; endoscopy
moistureresistance/capacitive probe, CM method, oven-dry weight
structure/moisture in depthultrasonic, seismic, radar, IR-thermography
masonry strengthunit cores + mortar joint strength; wallette (lab)tap/scratch + rebound as preselection
timberresistograph (bore resistance), glue-area lab tests, moisture, fastener corrosion (destructive), pest expert
steel membercoupons for composition/strength, weldability check, coating thickness (ultrasonic), lead/asbestos in old coatings

Site works order: photographic documentation → survey/control points → crack mapping incl. gauges on the building AND at neighbours → function checks of equipment → geometric control checks (dimensions, axes, storey heights vs. drawings) → actual use loads / occupancy audit → maintenance-state audit.

3.3 Pollutants (Schadstoffe) — periods to trigger testing

This is the start of the file. Read the full SKILL.md on GitHub.

Security

  • Security scanPassed, 100 of 100Pattern checks on the skill's files.
  • Model reviewNot runA model review is scheduled for the next rescan.

Quality evaluation

  • Task evaluationNot runNo evaluation yet. Run one in Skill Studio.

Source

Popularity

7-day trend score
0

Not refreshed yet.

Extension points

  • pluginCustom plugin integration

Works with

Any agent vskill installs to: 56 targets in all. These 39 have a page on this site.

  • Claude Code
  • Cursor
  • GitHub Copilot
  • Windsurf
  • Codex
  • Gemini CLI
  • Cline
  • Amp
  • Roo Code
  • Goose
  • Continue
  • Kilo Code
  • Junie
  • Trae
  • OpenHands
  • Qwen Code
  • AI Agent
  • Tabnine Chat
  • Sourcegraph Cody
  • Amazon Q
  • Firebase Genkit
  • Sweep
  • Devin
  • Phind
  • Mentat
  • Claude Desktop
  • Aider
  • GPT Pilot
  • Plandex
  • bolt.new
  • v0
  • Replit Agent
  • Anse
  • TypingMind
  • BetterChatGPT
  • LibreChat
  • Warp AI
  • Pieces
  • Fig AI
Embed badge
vskill VERIFIED badge
[![vskill VERIFIED](https://verified-skill.com/api/v1/skills/felixkarevo/construction-skills/existing-structures-retrofit/badge)](https://verified-skill.com/skills/felixkarevo/construction-skills/existing-structures-retrofit)

Something wrong with this skill or its page? Tell us.