Generate interactive HTML Gantt charts with Critical Path Method (CPM) analysis from task lists and dependencies, highlighting the critical path and calculating float times. Use when the user asks to create a Gantt chart, schedule project tasks, analyze the critical path, visualize dependencies, or mentions project timelines, milestones, or task scheduling.

Install

npx vskill@latest install serejaris/kimi-skills/gantt-planner

SKILL.md

The same SKILL.md was published earlier as serejaris/kimi-skills/gantt-planner.

gantt-planner -- Interactive Gantt Chart & Critical Path Analysis

Automatically performs Critical Path Method (CPM) analysis on task lists and their dependencies, generating interactive HTML Gantt charts. Supports zooming, critical path filtering, hover details, and dependency arrow visualization.

Quick Start

Simplest usage — pass JSON directly:

bash
python3 scripts/gantt_generator.py --json '{
"project": "New Product Launch",
"tasks": [
{"id": "T1", "name": "Requirements Analysis", "duration": 5, "dependencies": []},
{"id": "T2", "name": "UI Design", "duration": 4, "dependencies": ["T1"]},
{"id": "T3", "name": "Backend Development", "duration": 8, "dependencies": ["T1"]},
{"id": "T4", "name": "Frontend Development", "duration": 6, "dependencies": ["T2"]},
{"id": "T5", "name": "Integration Testing", "duration": 3, "dependencies": ["T3", "T4"]},
{"id": "T6", "name": "Deployment", "duration": 2, "dependencies": ["T5"]}
]
}' --output gantt.html

Read from a file with a specified start date:

bash
python3 scripts/gantt_generator.py --file tasks.json --start-date 2026-05-01 --output gantt.html

Methodology: Critical Path Method (CPM)

Core Concepts
TermAbbreviationMeaning
Earliest StartESThe earliest point at which a task can begin
Earliest FinishEFThe earliest point at which a task can be completed (ES + Duration)
Latest StartLSThe latest a task can start without delaying the project
Latest FinishLFThe latest a task can finish without delaying the project
Total FloatTFLS − ES; the number of days a task can be delayed
Critical Path—The sequence of tasks with zero float, determining the project's minimum duration
Calculation Steps
  1. Topological Sort: Order tasks by dependencies, detecting any circular references
  2. Forward Pass: Starting from the initial tasks, compute ES and EF for each task
  • ES = max(EF of all predecessors)
  • EF = ES + Duration
  1. Backward Pass: Working back from the final tasks, compute LS and LF
  • LF = min(LS of all successors)
  • LS = LF - Duration
  1. Identify the Critical Path: Tasks where float (LS − ES) equals 0 form the critical path

Input Format

A JSON object with the following fields:

json
{
"project": "Project Name",
"start_date": "2026-05-01",
"tasks": [
{
"id": "T1",
"name": "Task Name",
"duration": 5,
"dependencies": ["T0"]
}
]
}
FieldRequiredTypeDescription
projectNostringProject title; defaults to "Project Gantt Chart"
start_dateNostringYYYY-MM-DD format; can be overridden by the CLI --start-date flag
tasksYesarrayList of tasks
tasks[].idYesstringUnique task identifier
tasks[].nameYesstringTask name
tasks[].durationYesnumberDuration in days; must be > 0
tasks[].dependenciesNoarrayList of predecessor task IDs; defaults to []

Output Features

The generated HTML file is fully self-contained (no external dependencies) and includes the following interactive features:

  • Gantt Chart Visualization: Bar chart with time on the horizontal axis and tasks on the vertical axis
  • Critical Path Highlighting: Critical tasks in red, non-critical tasks in blue
  • Dependency Arrows: SVG-drawn dependency lines; critical dependencies are bold red
  • Float Time Display: Semi-transparent orange areas showing how much a task can be delayed
  • Hover Details: Hover over a task to see full CPM analysis data
  • Task Highlighting: Click a task to highlight its direct predecessors and successors
  • Zoom Control: Slider to adjust timeline granularity
  • Critical Path Filter: Toggle to show only critical path tasks
  • Today Marker: Green vertical line indicating the current date
  • JSON Export: Export the complete dataset with CPM annotations

Script Arguments

python3 scripts/gantt_generator.py [options]
Required (one of):
--json TEXT Task data as a JSON string
--file PATH Path to a JSON file containing task data
Optional:
--start-date DATE Project start date (YYYY-MM-DD); defaults to today
--output, -o PATH Output HTML file path; defaults to stdout
--title TEXT Override the project title

Full Example

Scenario: Software Development Project Schedule
json
{
"project": "CRM System v2.0 Development",
"start_date": "2026-05-05",
"tasks": [
{"id": "A", "name": "Requirements Research", "duration": 5, "dependencies": []},
{"id": "B", "name": "Architecture Design", "duration": 3, "dependencies": ["A"]},
{"id": "C", "name": "UI/UX Design", "duration": 4, "dependencies": ["A"]},
{"id": "D", "name": "Database Design", "duration": 2, "dependencies": ["B"]},
{"id": "E", "name": "Backend API Development", "duration": 10, "dependencies": ["D"]},
{"id": "F", "name": "Frontend Development", "duration": 8, "dependencies": ["C", "D"]},
{"id": "G", "name": "Unit Testing", "duration": 3, "dependencies": ["E"]},
{"id": "H", "name": "Integration Testing", "duration": 4, "dependencies": ["F", "G"]},
{"id": "I", "name": "User Acceptance Testing", "duration": 3, "dependencies": ["H"]},
{"id": "J", "name": "Deployment", "duration": 2, "dependencies": ["I"]}
]
}

Analysis results:

  • Total duration: 32 days
  • Critical path: A → B → D → E → G → H → I → J
  • UI/UX Design (C) has float time and can be delayed without affecting the total duration

Notes

  • Circular dependencies (A depends on B, B depends on A) are not allowed; the script detects and reports them
  • Duration is measured in calendar days; weekdays and holidays are not distinguished
  • All task IDs must be unique
  • The generated HTML can be opened offline — no internet connection required

Security

  • Security scanPassed, 100 of 100Pattern checks on the skill's files.
  • Model reviewPassed

Quality evaluation

  • Task evaluationNot runNo evaluation yet. Run one in Skill Studio.

Source

Popularity

Repository stars
7
Repository forks
3
7-day trend score
10

Stars and forks are for the whole GitHub repository, not this skill alone. Not refreshed yet.

Works with

Any agent vskill installs to: 56 targets in all. These 39 have a page on this site.

  • Claude Code
  • Cursor
  • GitHub Copilot
  • Windsurf
  • Codex
  • Gemini CLI
  • Cline
  • Amp
  • Roo Code
  • Goose
  • Continue
  • Kilo Code
  • Junie
  • Trae
  • OpenHands
  • Qwen Code
  • AI Agent
  • Tabnine Chat
  • Sourcegraph Cody
  • Amazon Q
  • Firebase Genkit
  • Sweep
  • Devin
  • Phind
  • Mentat
  • Claude Desktop
  • Aider
  • GPT Pilot
  • Plandex
  • bolt.new
  • v0
  • Replit Agent
  • Anse
  • TypingMind
  • BetterChatGPT
  • LibreChat
  • Warp AI
  • Pieces